04-06-04 Item 8TO: Honorable Mayor, Vice Mayor DATE: April 6, 2004 & City Commission FROM: Maria V. Davis AGENDA ITEM No. City Manager RE: Authorizing the City Manager to execute a Change Order for the Church Street Improvements — Phase 1 RESOLUTION: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF SOUTH MIAMI, FLORIDA, AUTHORIZING THE CITY MANAGER TO EXECUTE AN ADDITIONAL WORK ORDER (CHANGE ORDER) WITH T. J. PAVEMENT CORP. FOR THE CHURCH STREET IMPROVEMENTS -PHASE 1 CONSTRUCTION IN AN AMOUNT OF $19,975.00 TO BE CHARGED TO MIAMI -DADE COUNTY OFFICE OF COMMUNITY AND ECONOMIC DEVELOPMENT (OCED) GRANT ACCOUNT NUMBER 001 - 0000 -115 -7044; PROVIDING FOR AN EFFECTIVE DATE BACKGROUND & ANALYSIS: With proper management of the Church Street Improvements — Phase 1 project, the Public Works Department has been able to secure administrative fees in an amount of $17,200.00 for the project and have awarded a construction contract for $126,732.50 with installation of electrical conduits for new Florida Power & Lights in an amount of $6,188.00. All expenses to- date total $150,120.50 for an un- encumbered balance of $21,879.50. To avoid losing the un- encumbered grant amount, it is recommended to award additional construction work to the contractor (T.J. Pavement Corp.) out of the scope of work for Phase 2. The additional scope of work includes: supply and installation of two tapping sleeves to loop and increase water pressure along Church Street, pressure testing of each system and the resurfacing of the construction areas. This project will be funded from the fiscal year 2003 Community Development Block Grant through Miami -Dade County Community & Economic Development. The balance for the grant account is $21,879.50. RECOMMENDATION: It is recommended that the City Commission approve funding for the work. ATTACHMENTS: • Proposed Resolution • Contractor's proposal • Project location map 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 RESOLUTION NO A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF SOUTH MIAMI, FLORIDA, AUTHORIZING THE CITY MANAGER TO EXECUTE AN ADDITIONAL WORK ORDER (CHANGE ORDER) WITH T. J. PAVEMENT CORP. FOR THE CHURCH STREET IMPROVEMENTS -PHASE 1 CONSTRUCTION IN AN AMOUNT OF $19,975.00 TO BE CHARGED TO MIAMI -DADE COUNTY OFFICE OF COMMUNITY AND ECONOMIC DEVELOPMENT (OCED) GRANT ACCOUNT NUMBER 001- 0000 -115- 7044; PROVIDING FOR AN EFFECTIVE DATE WHEREAS, the Mayor and City Commission wishes to provide a much needed water main extension along Church Street, and WHEREAS, the Mayor and City Commission authorize the City Manager to execute a change order for additional construction under the contract with T.J. Pavement Corp. for construction of an additional water main extension along Church Street for an amount of $19,975.00. NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COMMISSION OF THE CITY OF SOUTH MIAMI, FLORIDA THAT: Section 1: The remaining funds from this OCED grant account number 001- 0000 -115 -7044 are being used to construct additional water main extension. Section 2: The water main extension will be constructed within the Church Street Improvements corridor. Section 3: The project is funded through the Miami -Dade County Office of Community & Economic Development, fiscal year 2003 Community Development Block Grant. Section 4: The Mayor and City Commission authorize the City Manager to execute a change order with T.J. Paving, Corp. for the construction of an additional water main extension within the Church Street Improvements corridor for an amount of $19,975.00 to be charged to account number 001 - 0000 -115 -7044. PASSED AND ADOPTED this day of 12004. ATTEST: APPROVED: CITY CLERK READ AND APPROVED AS TO FORM: CITY ATTORNEY MAYOR Commission Vote: Mayor Russell: Vice Mayor Palmer: Commissioner Wiscombe: Commissioner Sherar: Commissioner Birts- Cooper: Church Street Improvements — Phase 1 Additional Construction Services (Change Order) Contractor: T. J. Pavement Corp. Address: 11401 S. W. 40th Street Suite 335 Miami, Florida 33165 Project Location: SW 59th Place between SW 64th Street & SW 70th Street Item No. Work Description Quantity Unite Price Amount 1 Furnish & Install 8" x 8" Ductile Iron Pipe and tap 3 $2,068.33 $ 6,205.00 system. 2 Furnish and install 8" Gate Valve and pressure test 3 $1,800.00 $ 5,400.00 system. 3 Saw cut and asphalt restoration of all (3) project, L. S. L. S. $ 8,370.00 areas. Total: $19,975.00 Church Street SW 59 Place from SW 64 Street to SW 72 Street Church Street Project Area o 500 1,000 1 500 2 000 City of South Miami Feet