08-40-254120VAC BY
ELECTRICAL
CONTRACTOR
SYSTEM SPECIFIED IS BASED ON QEL GAS DETECTION SYSTEMS. MECHANICAL CONTRACTOR WILL BE RESPONSIBLE FOR ANY
CHANGES ARISING FROM USING AN ALTERNATE GAS DETECTION SYSTEM IN THIS PROJECT. PLEASE CONTACT MECHANICAL
SYSTEMS & CONTROLS AT 7968-229-9925 FOR PRICING B SYSTEM COORDINATION
MAIN CONTROL PANEL LOCATE ON
FIRST FLOOR ELECTRICAL ROOM
QEL
SENSOR NETWORK
MANUFACTURER'S REP IS REPONSIBLE
FOR SIZING MAIN TRANSFORMER TO
ENSURE PROPER VOLTAGE TO ALL
NETWORK TRUNKS
NETWORK RELAY MODULE
TO BE USED FOR
PRODUCT SPECIFICATIONS: CONTROL OF EXHAUST
FANS (SEE EXHAUST FAN
POWER SUPPLY 24VAC INTERLOCKS FOR
SIGNAL OUTPUT 2-10 VOLTS DETAILS)
OPERATING RANGE 0-125 PPM
SENSOR: ELECTROCHEMICAL
SENSOR TRANSMITTER MOUNTING: WALL MOUNTING
PROVIDE WITH RELAY OPTION -2 RELAYS 1 AMP SPDT AND BUZZER
PROVIDE KEY LOCK OF MAIN SYSTEM CONTROLLER AND PASSWORD PROTECTION TO PREVENT UNAUTHORIZED ACCESS
PROVIDE LCD DISPLAY OF CURRENT CO SYSTEM LEVEL AT EACH SENSOR AND AT THE M -CONTROLLER.
SYSTEMS WITHOUT ACTUAL INDICATION OF CO LEVEL AT THE SENSOR LEVEL ARE NOT ACCEPTABLE.
PROVIDE STARTUP AND OWNER TRAINING OF GAS DETECTION SYSTEM
SYSTEM MUST BE CAPABLE OF BEING CONNECTED TO OTHER INDUSTRIAL GRADE SYSTEMS OR BAS VIA MODBUS PROTOCOL
SYSTEM MUST BE A NETWORKED SYSTEM. SYSTEMS REQUIRING MULTIPLE SENSORS TO BE HOME RUN TO A CENTRAL PANEL
WILL NOT BE ACEPTABLE AS THEY WILL INCREASE THE ELECTRICAL COST OF THE PROJECT.
PROVIDE SUBMITTAL WITH SEQUENCE OF OPERATIONS FOR APPROVAL BY MECHANICAL ENGINEER
SENSOR MUST BE INSTALLED 4-6 FEET FROM FLOOR. PROVIDE FINAL AS BUILT SUBMITTALS.
GAS DETECTION SYSTEM ONE LINE RISER DIAGRAM
See Plans For Specific Locations And Quantities Of Sensors
PROVIDE Y' Conduit with pull string for carbon
monoxide system. Number of sensors and locations
are shown on mechanical plans. provide conduit to
starters for each fan controlled as part of the system.
Provide 120VAC Power To Main Controller. Location
shown on mechanical Plans. CO System
Manufacturer's Rep Shall Provide Transformer, Wire
Terminations and Startup Of The CO System.
TYPICAL SENSOR WITH LCD DISPLAY OF
ACTUAL PPM READING SEE PLANS FOR
QUANTITIES i LOCATIONS
0 rolO O
O 1 a I
TYPICAL SUPPLY OR
EXHAUST FAN TO BE
CONTROLLED
SYSTEM AND RELATED TRADE RESPONSIBILITY
EXHAUST FAN INTERLOCKS
EXHAUST FAN INTERLOCK AREA
EF -1
PARKING GARAGE CO SENSORS
EF -2
PARKING GARAGE CO SENSORS
EF -3
PARKING GARAGE CO SENSORS
EF -4
PARKING GARAGE CO SENSORS
SYSTEM AND RELATED TRADE RESPONSIBILITY
DESCRIPTION
RESPONSIBLE
QEL CONTROLLER
MANUFACTURER'S REPRESENTATIVE
CONTROL WIRING
MANUFACTURER'S AUTHORIZED ELECTRICAL CONTRACTOR
SYSTEM STARTUP
MANUFACTURER AUTHORIZED STARTUP AGENT
CONTROL CONDUIT
DIVISION 16 ELECTRICAL CONTRACTOR
POWER WIRING
DIVISION 16 ELECTRICAL CONTRACTOR
120 VAC (DIV 16s) SEE ROOM DESIGNATION FOR THIS SYSTEM IN
MECHANICAL PLAN LFKD I
TYPICAL SUPPLY OR
EXHAUST FAN TO BE
CONTROLLED
QEL NETWORKED CARBON MONOXIDE TYPICAL SENSOR WITH LCD DISPLAY
SYSTEM CONTROLLER.
CONDUIT LAYOUT FOR CARBON MONOXIDE SYSTEM DIV16
See Plans For Specific Locations And Quantities Of Sensors
VENTILATION RISER
SEE FLOOR PLAN
FOR SIZES
DUCTWORK.SEE
FLOOR PLAN
FOR CONTINUATION
SEAL ALL AROUND
DUCT PENETRATION
TO MAINTAIN FIRE
RATING INTEGRITY
SHAFT WALL.
REFER TO ARCH. DWGS.
SHEETMETAL DUCT
(WHERE SPECIFIED)
SUBDUCT
TYPICAL SUBDUCT DETAIL
N.T.S.
SYSTEM AND RELATED TRADE RESPONSIBILITY
SUPPLY; EXHAUST FAN INTERLOCKS
EXHAUST FAN INTERLOCK AREA
EF -1
PARKING GARAGE CO SENSORS
EF -2
PARKING GARAGE CO SENSORS
EF -3
PARKING GARAGE CO SENSORS
EF -4
PARKING GARAGE CO SENSORS
SYSTEM AND RELATED TRADE RESPONSIBILITY
DESCRIPTION
RESPONSIBLE
QEL CONTROLLER
MANUFACTURER'S REPRESENTATIVE (MSC 796-229-8925)
CONTROL WIRING
MANUFACTURER'S AUTHORIZED ELECTRICAL CONTRACTOR
SYSTEM STARTUP
MANUFACTURER AUTHORIZED STARTUP AGENT (MSC 7968-226-6925)
CONTROL CONDUIT
DIVISION 16 ELECTRICAL CONTRACTOR
POWER WIRING
DIVISION 16 ELECTRICAL CONTRACTOR
HVAC NOTES
1.0 GENERAL
1.1 PROVIDE ( FURNISH AND INSTALL ) ALL NECESSARY
MATERIALS AND LABOR FOR A COMPLETELY OPERATIONAL
AIR CONDITIONING, HEATING AND VENTILATING SYSTEM AS
SHOWN ON THE DRAWINGS AND HEREIN SPECIFIED
1.2 INSTALL IN ACCORDANCE WITH THE FLORIDA
BUILDING CODE, ASHRAE, SMACNA, NFPA AND LOCAL
ORDINANCES.
1.3 SCOPE OF WORK :
PROVIDE THE FOLLOWING COMPLETE SYSTEMS ;
A. SUPPLY AND RETURN DUCT SYSTEM.
B. EXHAUST SYSTEM FOR TOILET ROOMS.
C. AIR CONDITIONING UNITS WITH REFRIGERANT PIPING
AND CONTROLS FOR OFFICES.
D. EMERGENCY GENERATOR EXHAUST PIPING & INSULATION.
E. INDEPENDENT TEST AND BALANCE.
1.4 CONTRACTOR MUST BE FAMILIAR WITH THIS TYPE OF INSTALLATION
AND THOROUGHLY UNDERSTAND ALL THE REQUIREMENTS FOR
THE INSTALLATION OF EACH PIECE OF EQUIPMENT HEREIN SHOWN.
ITS PROPER OPERATION REQUIREMENTS AND TESTING
PROCEDURES FOR CITY APPROVALS.
1.5 PAY FOR ALL FEES, INSPECTIONS AND CONNECTION
CHARGES REQUIRED
1.6 VERIFY AT JOB SITE ALL SPACE CONDITIONS, DIMENSIONS
AND EQUIPMENT SIZES PRIOR TO DUCT FABRICATION OR
INSTALLATION. COORDINATE REQUIREMENTS TO AVOID
INTERFERENCE WITH OTHER TRADES.
1.7 NATURE OF DESIGN DRAWINGS:
DESIGN DRAWINGS ARE DIAGRAMMATIC AND DO NOT INTEND
TO SHOW EVERY FITTING, ELBOW, TRANSITION, ETC. THAT
WILL BE NECESSARY FOR A COMPLETE OPERATIONAL SYSTEM
AS REQUIRED BY THESE SPECIFICATIONS.
1.8 COORDINATION DRAWINGS:
PREPARE 1/4" SCALE COORDINATION DRAWINGS SHOWING
MAJOR SYSTEM COMPONENTS FOR A/E APPROVAL.
1.9 SUBMIT SHOP DRAWINGS FOR ARCHITECT / ENGINEER
APPROVAL BEFORE PROCEEDING WITH THE PURCHASE OR
INSTALLATION OF EQUIPMENT AND MATERIALS.
SUBMIT AL AT ONCE IN A BINDER WITH AN INDEX AND DIVIDERS AS
REQUIRED TO SEPARATE ALL DIFFERENT MATERIALS AND EQUIPMENT.
1.10 GUARANTEE ALL WORK FREE OF DEFECTS IN MATERIALS
AND WORKMANSHIP FOR A PERIOD OF ONE YEAR FROM
DATE OF ACCEPTANCE.
2.0 MATERIALS
2.1 DUCTWORK: ALL JOINTS SEALED WITH HIGH PRESSURE MASTIC.
2.1.1 GENERAL. ALL DUCT SIZES SHOWN ARE CLEAR INSIDE
DIMENSIONS.
2.1.2 DUCTWORK MATERIALS:
A: GENERAL PUBLIC AREAS:
FIVE POUNDS DENSITY 1.5" THICK GLASS FIBER (R-6)
DESIGNED, CONSTRUCTED AND INSTALLED IN ACCORDAANCE
WITH SMACNA'S LOW PRESSURE DUCT MANUAL. ALL
DUCT JOINTS SHALL BE SEALED AND TAPED.
B: TOILETS ROOM EXHAUST AND FRESH AIR INTAKES:
GALVANIZED SHEET METAL, CONSTRUCTED, AND INSTALLED
ACCORDING TO LATEST EDITION OF SMACNA'S. LOW
PRESSURE CONSTRUCTION STD. (0.5" W.G.
SEAL ALL JOINTS WITH APPROVED FIRE MED MASTIC.
C: CORRIDORS SUPPLY AIR RISER
GALVANIZED SHEET METAL, CONSTRUCTED, AND INSTALLED
ACCORDING TO LATEST EDITION OF SMACNA'S. LOW
VELOCITY CONSTRUCTION STD. FOR 2" STATIC PRESSURE.
INSULATE WITH 1-1/2" THICK FIBERGLASS BLANKET INSULATION
WITH APPROVED FIRE do SMOKE REINFORCED ALUMINUM JACKET.
D: ROUND INSULATED FLEXIBLE DUCT
PROVIDE AS SHOWN ON PLANS, WIREMOLD WCK
W 1-1/2" INSULATION & REINFORCED ALUM. VAPOR
OR APPROVED EQUAL.
MAXIMUM LENGTH PERMITTED PER RUNOUT = 5'-0"
2.1.3 DUCT INSULATION: (ALL A/C SUPPLY do RETURN)
1-1 2" THICK, 1-1/2 LB. DENSITY GLASS FIBER BLANKET
WITH REINFORCED ALUMINUM FOIL VAPOR BARRIER.
SEAL ALL JOINTS WITH APPROVED FIRE RATED MASTIC.
2.1.4 ACOUSTICAL LINING: (ALL A/C SUPPLYk RETURN)
LINE FIRST 10 FT FROM UNIT WITH 1, THICK GLASS FIBER
MATT FACED. PAINT WITH ANTIBACTERIAL COATING.
ATTACH TO DUCT WITH APPROVED SMACNA PROCEDURE.
2.1.5 DUCTWORK ACCESSORIES:
A. PROVIDE DOUBLE THICKNESS TURNING VANES AT ALL
SQUARE ELBOWS. WHERE THE ELBOWS ARE RECTANGULAR
INSTALL SINGLE THICKNESS INSTEAD.
.1 ALTERNATE A: PROVIDE 3 -PIECE ELBOWS IN LIEU
OF TURNING VANES FOR GLASS FIBER DUCTS ONLY.
.2 ALTERNATE A: PROVIDE FULL RADIUS ELBOWS IN LIEU
OF TURNING VANES.
B. PROVIDE VOLUME EXTRACTORS BEHIND EACH SUPPLY
OUTLET AND AT EACH DUCT BRANCH.
2.2 AIR DISTRIBUTION PRODUCTS
2.2.1 PROVIDE SUPPLY AND RETURN GRILLES AND DIFFUSERS
AS INDICATED ON THE DRAWINGS.
2.2.2 PROVIDE EXTRUDED ALL ALUMINUM AIR DISTRIBUTION
PRODUCTS.
2.2.3 PROVIDE FINISHES AND TYPES OF MOUNT IN COORDINATION
WITH THE CEILING TYPES AS SHOWN ON ARCHITECTURAL
DRAWINGS.
2.2.4 PROVIDE OPPOSED BLADE, KEY OPERATED DAMPERS
BEHIND ALL AIR SUPPLY OUTLETS.
2.3 PIPING:
2.3.1 REFRIGERANT PIPING. SEAMLESS COPPER TYPE "L" AND
HARD OR SOFT DRAWN ON ACR COPPER TUBING WITH
WROUGHT COPPER BRAZED JOINT FITTINGS, WITH SILVER
BRAZING CONTAINING NOT LESS THAN 49% SILVER.
2.4 NOT USED
2.5 INSULATION:
2.5.1 INSULATE ALL REFRIGERANT SUCTION PIPING WITH 3/4"
CLOSED CELL POLYETHYLENE PRE MOLDED
INSULATION, WITH AN APPROVED PIPE AND SMOKE
JACKET. PAINT ALL EXPOSED INSULATION WITH TWO
COATS OF WHITE LATEX PAINT.
2.5.2 NOT USED
2.5.3 INSULATE GENERATOR EXHAUST PIPE AND MUFFLERS
WITH 1-1/2" CALCIUM SILICATE INSULATION.
PROVIDE .016" THICK ALUMINUM JACKET.
2.6 ALL AIR CONDITIONING COMPRESSORS SHALL BE
WARRANTED FOR A MINIMUM OF FIVE YEARS AFTER DATE
OF ACCEPTANCE OF THE PROJECT.
2.7 CONTROLS:
2.7.1 GENERAL: PROVIDE THE NECESSARY AUTOMATIC CONTROLS FOR
PROPER OPERATION OF ALL EQUIPMENT SPECIFIED HEREIN.
FURNISH MAGNETIC STARTERS AND INTERLOCK WIRING
INDICATED FOR EACH PIECE OF EQUIPMENT.
2.7.2 PUBLIC AREA DX EQUIPMENT:
PROVIDE AIR CONDITIONING UNITS WITH PROGRAMMABLE MATCHING
LOW VOLTAGE HEAT -COOL THERMOSTATS WITH ON --OFF AUTO
SUB -BASE SWITCH, FURNISHED BY THE EQUIPMENT
MANUFACTURER WITH HEAT -COOL STEPS AS REQUIRED.
2.7.3 CONTROL WIRING:
PROVIDE (FURNISH i INSTALL) 'OWER SUPPLY WIRING SOURCE
TO POWER CONNECTION, INCLUDE STARTERS, DISCONNECTS
AND REQUIRED ELECTRICAL DEVICES, INTERLOCK WIRING,
RACEWAY, CONDUITS, PULL WIRES AND EXPOSED CONDUITS
FOR TEMPERATURE CONTROL SYSTEM. ALL WIRING SHALL RUN
IN CONDUITS, NO EXCEPTION
2.7.4 CONTROL WIRING:
PROVIDE (FURNISH & INSTALL) POWER SUPPLY WIRING SOURCE
TO POWER CONNECTION, INCLUDE STARTERS, DISCONNECTS
AND REQUIRED ELECTRICAL DEVICES, INTERLOCK WIRING,
RACEWAY, CONDUITS, PULL WIRES AND EXPOSED CONDUITS
FOR TEMPERATURE CONTROL SYSTEM. ALL WIRING SHALL RUN
IN CONDUITS, NO EXCEPTION
2.8 STARTERS:
PROVIDE MAGNETIC STARTER FOR ALL MECHANICAL EQUIPMENT
IN THIS SECTION, OF TYPE DESCRIBED ON THE SCHEDULES
WITH HAND -OFF -AUTO BUTTON POSITIONS ON THE COVER
AND RED -GREEN PILOT LIGHTS.
PROVIDE THE NECESSARY AUXILIARY OPEN AND CLOSED CONTACTS
FOR THE INTENDED OPERATION AND INTERLOCKS.
2.9 IDENTIFICATION:
2.9.1 LABEL ALL EQUIPMENT WITH ENGRAVED BLACK PLASTIC
PLAQUES 12 " x 4" HIGH WITH 1.5' LETTERS.
3.0 EXECUTION
3.1 INSTALL ALL EQUIPMENT AND MATERIALS IN STRICT ACCORDANCE
WITH THE MANUFACTURER'S MANUALS AND RECOMMENDATIONS,
PAYING SPECIAL ATTENTION TO REQUIRED CLEARANCES
FOR INSTALLATION, OPERATION AND SERVICE.
3.2 SEAL ALL DUCT JOINTS WITH APPROVED FIRE AND SMOKE RATED
HIGH PRESSURE MASTIC.
3.3 THERMOSTAT LOCATION.
THERMOSTAT LOCATION IS CRITICAL TO PROPER EQUIPMENT OPERATION.
INSTALL THERMOSTAT AT LOCATIONS SHOWN ON PLANS.
RELOCATE ONLY WHEN APPROVED BY THE A/E IN WRITING.
34 WHERE R/A IS PROPOSED BY WAY OF DOOR UNDERCUTS, PROVIDE A MINIMUM
1" CLEAR SPACE BETWEEN THE BOTTOM OF THE DOOR AND THE FLOOR FINISH
CARPET OR TILE.
3.5 EQUIPMENT MUST OPERATE FREE OF OBJECTIONABLE NOISE AND VIBRATION
REPAIR AND/OR REPLACE ALL SOURCES OF NOISE AND VIBRATION FOUND
TO BE OBJECTIONABLE, TO THE SATISFACTION OF THE A/E.
3.6 BALANCE ALL SYSTEMS TO PROVIDE AIR QUANTITIES AND CAPACITIES
TO MATCH SPECIFIED FLOWS & CAPACITIES.
NOTIFY A/E OF ANY DEFICIENCIES NOTED DURING TESTING is BALANCING
CALIBRATE FLOWS TO NEW EQUIPMENT PER MANUFACTURER'S REQUIREMENTS.
BEFORE COMPLETING TEST & BALANCE PROCEDURES.
ALLOW NECESSARY TIME FOR IMPLEMENTING PROPOSED SOLUTIONS
BEFORE CONTINUING WITH TEST do BALANCE.
AT END OF TEST AND BALANCE ISSUE A COMPLETE REPORT FOR A/E
APPROVAL AND ALLOW TIME AND PROVIDE NECESSARY INSTRUMENTS
FOR SPOT CHECKING WITH A/E.
SUBMIT FINAL TEST AND BALANCE REPORT TO A/E FOR ACCEPTANCE.
AIR QUANTITIES SHOWN ARE TO BE ADJUSTED AS REQUIRED
TO MEET SPECIFIC JOB CONDITIONS.
3.9 STRICTLY FOLLOW ALL MANUFACTURER'S INSTALLATION MANUALS AND
INSTRUCTIONS IN THE INSTALLATION OF ALL EQUIPMENT.
OBTAIN, FROM EACH MANUFACTURER, PROPER CERTIFICATION FOR
THE ADEQUACY OF THE INSTALLATION OF ALL PIECES OF EQUIPMENT
BEFORE PLACING SYSTEM IN OPERATION.
3.10 PROVIDE MAINTENANCE AND OPERATION MANUAL
3.11 PROVIDE AS -BUILT REPRODUCIBLE DRAWINGS.
3,12 PROVIDE INSTRUCTION TO OWNER'S DESIGNATED PERSONNEL.
(� �" . V •iV u V V V
• • i V • • V V "
„ • • V • Y y i
•
y • • • � u u•• Y V
VUY i
V•• i u • u V V W Y •
V • V . V
V Y ,, • ` Y • y • u V Y V V Y
• y u • V i • V y •
V• Y• Y Y G V Y V • • •
y �
y V•• V V I• V
Y • uyu Y•r•
• • C V • Y
V • • 4 y
•u•• Y • u
• ••VYu y V •
V G i • ••44• V
CITY OF SC)UTFI &11AIPAI
I~it..IIL_I)!IN, 1 j DEPT.
I "ECFIAPI:CAL SECTION'
APPR0VED BY:
wo i`rR,t i
•R
#268000522
1+I
6
e.} V
Ca
4 �
C �
C:1 �
W r-
U
r sc
Lu
W
N M
iL
W 'C
b h
� W
o
_ N
m
o
O N
� o
C �
J W
_o
M
b N
o�
� b
f �
� W
ti
w
2 C
U �
C V
w
ARCHITECTURE INTERIOR DESIGN PLANNING
SEAL
MONEY J. MATEU
AR 0008220
JMM CONSULTING ENGINEERS, LLC
M.E.P.
12651 S DIXIE HIGHWAY, SUITE 209
MIAMI, FLORIDA 33155
M.A. SUAREZ CONSULTING ENGINEERS
STRUCTURAL ENGINEERING
4869 SW 75TH AVENUE
MIAMI, FLORIDA 33155
INISTORINO & ALAM CONSULTING ENG. INC.
CIVIL ENGINEERING
7171 SW 62ND AVENUE, 4TH FLOOR
MIAMI, FLORIDA 33143
OXFORD UNIVERSAL
4311 PONCE DE LEON BLVD.
CORAL GABLES, FLORIDA 33146
5966 SOUTH
DIXIE BUILDING
5966 & 5970
SOUTH DIXIE HIGHWAY
MIAMI, FLORIDA 33133
MATEU ARCH ITEGTURE INC.
THIS DRAWING IS THE PROPERTY OF MATEU
ARCHITECTURE INC. UNLESS OTHERWISE PROVIDED
FOR NY CONTRACT. THE CONTLNTS OF THIS
DRAWING ARE CONFIDENTIAL AND SHALL NOT
DE TRANSMITTED TO ANY PARTY EXCEPT AS
AUTHORIZED NY THE ARCHITECT/ENGINEERS OF
RECORD.
PHASE
PERMIT DRAWINGS
FILE NAME
M -204 -DWG
PROJECT NO:
MA0605
DRAWN 6Y
JMM
CHECKED BY;
JMM
ISSUE DATE:
DECEMBER 10, 2007
REVISIONS
SHEET TITLE
MECHANICAL NOTES
SHEET: OF: /
M-204 12 i