11-1105-005FORM 1100A-08
Code Compliance Checklist
Residential Whole Building Performance Method A - Details
ADDRESS: 6875 sw 69 terrace PERMIT #:
Miami, FI, 33143-
INFILTRATION REDUCTION COMPLIANCE CHECKLIST
COMPONENTS
SECTION
REQUIREMENTS FOR EACH PRACTICE
CHECK
Exterior Windows & Doors
N1106.AB.1.1
Maximum:.3 cfm/s .ft. window area; .5 cfm/s .ft. door area.
Exterior & Adjacent Walls
N1106.AB.1.2
Caulk, gasket, weatherstrip or seal between: windows/doors &
frames, surrounding wall; foundation & wall sole or sill plate; joints
between exterior wall panels at comers; utility penetrations;
between wall panels & top/bottom plates; between walls and floor.
EXCEPTION: Frame walls where a continuous infiltration barrier is
installed that extends from, and is sealed to, the foundation to the
top plate.
Floors
N1106.AB.1.2
Penetrations/openings > 1/8" sealed unless backed by truss or
joint members.
EXCEPTION: Frame floors where a continuous infiltration barrier
is installed that is sealed to the perimeter, penetrations and seams.
Ceilings
N1106.AB.1.2
Between walls & ceilings; penetrations of ceiling plane to top floor,
around shafts, chases, soffits, chimneys, cabinets sealed to
continuous air barrier; gaps in gyp board & top plate; attic access.
EXCEPTION: Frame ceilings where a continuous infiltration barrier
is installed that is sealed at the perimeter, at penetrations and
seams.
Recessed Lighting Fixtures
N1106.AB.1.2
Type IC rated with no penetrations, sealed; or Type IC or non -IC
rated, installed inside a sealed box with 1/2" clearance & 3" from
insulation; or Type IC with < 2.0 cfm from conditioned space,
tested.
Multi -story Houses
N1106.AB.1.2
Air barrier on perimeter of floor cavity between floors.
C
Additional Infiltration reqts
N1106.AB.1.3
Exhaust fans vented to outdoors, dampers; combustion space
heaters comply with NFPA, have combustion air.
OTHER PRESCRIPTIVE MEASURES (must be met or exceeded by all residences.)
COMPONENTS
SECTION
REQUIREMENTS
CHECK
Water Heaters
N1112.AB.3
Comply with efficiency requirements in Table N1112.ABC.3
Switch or clearly marked circuit breaker (electric) or cutoff (gas)
must be provided. External or built-in heat trap required.
Swimming Pools & Spas
N1112.AB.2.3
Spas & heated pools must have covers (except solar heated).
Non-commercial pools must have a pump timer. Gas spa & pool
heaters must have a minimum thermal efficiency of 78%.
Heat pump pool heaters shall have a minimum COP of 4.0.
Shower heads
N1112.AB.2.4
Water flow must be restricted to no more than 2.5 gallons per
minute at 80 PSIG.
Air Distribution Systems
N1110.AB
All ducts, fittings, mechanical equipment and plenum chambers
shall be mechanically attached, sealed, insulated and installed in
accordance with the criteria of Section N1110.AB.
Ducts in unconditioned attics: R-6 min. insulation.
HVAC Controls
N1107.AB.2
Separate readily accessible manual or automatic thermostat for
each system.
Insulation
N1104.AB.1
Ceilings -Min. R-19. Common walls -frame R-11 or CBS R-3 both
N1102.13.1.1
sides. Common ceiling & floors R-11.
9/20/2011 4:08 PM EnergyGaugeO USA - FlaRes2008
Page 5 of 5