Res No 061-17-14862RESOLUTION NO.: 061-17-14862
A Resolution authorizing a temporary change in the permitted hours of construction
operations of Florida Power & Light (FPL) to perform work on SW 62 Avenue, between SW 70th
Street and South Dixie Highway.
WHEREAS, Pursuant to Section 7-16(g) of Code of the Ordinances, as amended by Ordinance
No. 5-15-2212, all construction sites shall comply with the city's noise code and it provides in pertinent
part as follows:
All construction sites shall comply with the city's noise code. Construction activity is limited to the hours
of 7:00 a.m. through-6:00 p.m. on the weekdays of Monday thru through Friday; and between the hours
of 9:00 a.m. through 5:00 p.m. on Saturday. No construction activity is permitted on Sunday.
Notwithstanding the above, no construction activities shall take place in, or within 500 feet of,
residentially zoned districts, other than those in the Hometown District, on either Saturday or Sunday
and, as to construction activities in non-residentially zoned districts and in the Hometown District, all
days of the week and hours of the day may be changed by resolution of the City Commission upon a
finding of extraordinary circumstances.
WHEREAS, FPL wishes to perform work along SW 62 Avenue, between SW 70th Street and South
Dixie Highway to replace existing transmission line concrete poles along the east side of SW 62 Avenue;
and
WHEREAS, the transmission line clearances are only available during the night and the type of
equipment being used will impact traffic due to a required lane closure. In addition, the FPL's operations
at night will cause minimal traffic impact; and
WHEREAS, allowing construction activities at night may be changed by resolution of the City
Commission upon its finding of extraordinary circumstances; and
WHEREAS, FPL is requesting authority to conduct transfer services during night hours; and
WHEREAS, approval of this request will not be detrimental or harmful to the surrounding area
of the community at large.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COMMISSION OF THE CITY OF
SOUTH MIAMI, FLORIDA THAT:
Section 1: The recitals set forth above have been found to be true and they are hereby
incorporated by reference as if fully set forth herein. The construction hours are hereby changed
temporarily for the current construction activities of FPL for three weeks, from the date of permit
issuance or until such time as the City Commission or the City Manager revokes these extended hours of
operation. The temporary hours of construction operations are limited to the hours of 9:00 PM to 6:00
AM. The contractor shall hire, at their own expense, an off duty City of South Miami Police officer for
these days and during these hours to insure that the FPL complies with the City's ordinances and this
resolution. The extended hours for construction activity authorized by this Resolution may also be
reduced or revoked upon determination of the City Manager in his sole and absolute discretion that a
violation of any of the City's ordinance or this Resolution has occurred and has not been resolved to his
satisfaction or that the noise level is otherwise excessive. This resolution may be revoked at any time in
the sole and absolute discretion of the City Commission.
Pg. 2 of Res.!No. 061-17-14862
Section 2. Severability. If any section clause, sentence, or phrase of this resolution is for any
reason held invalid or unconstitutional by a court of competent jurisdiction, the holding shall not affect
the validity of the remaining portions of this resolution.
Section 3. Effective Date. This resolution shall become effective immediately upon adoption by
vote of the City Commission.
PASSED AND ADOPTED this 4 th day of Apr i 1 ,2017.
COMMISSION VOTE: 5-0
Mayor Stodd~rd Yea
Vice Mayor Welsh Yea
Commissioner Harris Yea
Commissioner Liebman Yea
Commissioner Edmond Yea
THE CITY OF PLE ASAN T LIVI NG
CITY OF SOUTH M IAMI
OFFICE O F THE C ITY MANAG ER
INTER-OFFICE M EMOR AN D UM
To: The Honorable Mayor & Members of the City Commission
FROM: Steven Alexander, City Manage r
Age nda Item No.:l DATE: April 4, 2017
SUBJECT: A Resolution authorizing a temporary change in the permitted hours of
construction operations of Florida Power & Light (FPL) to perform work on SW
62 Avenue, between SW 70th Street and South Dixie Highway.
BACKGROUND: Ordinance No. 5-15-2212 prohibits construction activity to take place during
night hours from 6:00 PM though 7:00 AM. FPL is transferring / replacing
existing transmission line concrete poles along the east side of SW 62 Avenue as
per the City's request to comp ly with ADA requirements to allow safe passage of
bicycles and pedestrians.
REQUEST:
AMOUNT:
ACCOUNT:
Due to Heavy traffic during daylight hours on SW 62 Avenue, and because the
electric transmission lines require traffic clearances during movement between
poles which are only available during the night for this area, FPL is requested a
waiver, to allow them to work during night hours.
The Resolution attached is to wa ive the limitatio n on hours of construction, as
authorized by the Or dinance. The work is anticipated to be completed within
the next two weeks .
Not applicable
Not applicable
ATTACHMENTS: Resolution
Request from FPL
Ordinance No. 5-15-2212
I=PL
Tuesday, March 07,2017
City of South Miami
Engineering & ConstlUction Division
Attn: Ms. Grizel Martinez
4795 SW 75 th Avenue
Miami, Florida 33155
(305) 403-2063; Fax (305) 668-7208
RE: Request for Night Work
Utility Notification of Proposed Construction
SW 62 nd Avenue Right-of-Way
City of South Miami
Miami-Dade County
FPL 10# T00000015275
Dear Ms . Martinez:
P.O. BOX 14000. JUNO BEACH, FL 33408-0420
Due to Disu'ibution line clearances available only during nighttime and early morning hours, Florida
Power and Light Company respectfully request a resolution to waive the limitation on hours of
constlUction and to authorize nighttime hours for the proposed constlUction.
The location is along SW 62 11d Avenue between SW 70 th Street and S Dixie Highway. The proposed
construction is to facilitate the transfer of Distribution underbuilt facilities to newly installed
replacement poles, the removal of the replaced poles, and includes the restoration of the consuuction
areas and any sidewalks damaged. Traffic control will confmm to FDOT's Roadway and Traffic
Control Standards. Construction is scheduled to begin as soon as the resolution is approved.
If you have any questions and! or comments peliaining to tins request, please call Natalie Borrelli,
Transmission Engineer at (954) 717-3120 01' Rafael Vides at (561) 904-3692 .
Thank you in advance for your assistance in tills matter.
Please mail 01' email approval to : FPL, Attn: Rafael Vides (TS4/JW)
700 Universe Blvd.
Sincerely,
4~/
Gregg Hall
Florida Power & Light Company
Manager -Siting & Permitting
all FI'L G roup company
Juno Beach, Florida 33408
rafael . e. vides@fpl .com
r=PL
Thursday, March 02,2017
City of South Miami
Engineering & Construction Division
Attn: Ms. Grizel Martinez
4795 SW 75 th Avenue
Miami, Florida 33155
(305) 403-2063; Fax (305) 668-7208
RE : Power Line Maintenance Work
Utility Notification of Proposed Construction
SW 62 0d Avenue Right-of-Way
City of South Miami, Dade County
P.O. BOX 14000 , JUNO BEAC H, FL 33408·0420
Cutler-South Miami 138kV Transmission Line, FPL 10# T00000015275
Dear Ms. Martinez:
Enclosed for your review are one (1) permit application and one (1) copy of our drawings detailing
Florida Power & Light's proposed overhead power line construction in the City of South Miami, Dade
County, Florida.
The scope of work will entail the transfer of Distribution underbuilt facilities , the removal of the double
poles, and restoration of the sidewalk located along the east side of SW 62nd Avenue between SW 70th
Street and S Dixie Highway due to maintenance requirements. Traffic control will conform to FDOT's
Roadway and Traffic Control Standards . This project will required night work. Construction is
scheduled to begin on March 8, 2017.
If you have any questions and/or comments pertaining to this request, please call Natalie Borrelli,
Transmission Engineer at (954) 717-3120 or Rafael Vides at (561) 904-3692 .
Thank you in advance for your assistance in this matter.
Please mail the approved permit to: FPL, Attn: Rafael Vides (TS4/JW)
700 Universe Blvd.
Sincerely,
d~/-r;/vi /Co:~Hal1
Florida Power & Light Company
Manager -Siting & Permitting
an FPL G ro up cO lllp any
Juno Beach, Florida 33408
rafael .e . vides@fpl.com
THE CITY OF SOUTH MIAMI ~i
PUBLIC WORKS AND ENGINEERING DEPARTMENT { IA }
4795 SW 75 th Avenue, M i am i, Florid a 33155 • •
PI .. "" 305-403-2063 F'" 305-668-7208 Soutn'Mlaml
E-mail : Engineering@SouthMiamiFL.gov
THE CITY O F PL EA SANT LIVING
PERMIT #
PERMIT APPLICATION FOR WORK WITHIN THE PUBLIC RIGHT-OF-WAY
Note: all fields shall be filled
PROJECT LOCATION: Al ong the east side of SW 62nd Avenue between SW 70th Street and S Dixie Highway
Natalie Borrelli (Project Enginee r) at (954) 717-3120
APPLICANT : Fl orida Power and Light Company Rafael Vi des at (561) 904-3692
NAME OF CO MPANY NA ME OF CONTACT
Natalie .Borrel li @fpLcom
PHONE/CELL # (954) 494-5360 , Mobile E-MAIL : RafaeLE.Vides@fpLcom -----------=~---------------------
APPLICANT'S ADDRESS : 700 Universe Boulevard (TS4/JW)
STREET ADDRESS
Juno Bea ch
CITY
I HEREBY REQUEST A PERMIT FOR THE FOLLOWING (BE SPECIFIC):
Flo rida 33408
STATE ZIP
The scope of work will entail the transfer of Distribution underbuilt facilities , remova l of the double .poles , and
restorat ion of th e sidewalk . This project will required night work .
Cutler-So uth Miam i 138kV Transm iss ion Line, FPL 10# T00000015275 .
PROJECT DURATION: Start date : 3/8/17 , End date : 4/30/17
DATES (FROM -TO), DURATION
ESTIMATED PROJECT COST: $ 75,0 00 .00
THE FOLLOWING HAS BEEN SUBMITTED WITH THIS PERMIT APPLICATION:
TWO SETS OF PLANS, SKETCHES AND OTHER DOCUMENTATION DESCRIBING THE PROPOSED WORK ............................. 0
MAINTENANCE OFTRAFFIC (MOT) FOR VEHICULAR AND PEDESTRIAN TRAFFIC DURING PROJECT .................................. 0
COUNTY OR STATE LICENSE AND CERTI FICATE OF INSURANCE (COPIES ARE ACCEPTABLE) ............................................... 0
PERFORMANCE BOND ........................................................................................................................................................... 0
"BEFORE" PICTURES (NOTE THAT "AFTER" PICTURES SHALL BE SUBMITIED UPON COMPLETION OF WORK) ................... O
CALL 811 FROM ANYWHERE IN FLORIDA TWO FULL BUSINESS DAYS BEFORE DIGGING.
"IN SIGNING THIS APPLICA TlON, I UNDERSTAND THAT SEPARATE CITY AND/OR COUNTY
PERMITS MAY BE REQUIRED FOR THIS PROJECT . FURTHERMORE, I AM AWARE THAT I AM
RESPONSIBLE FOR ENSURING THAT THE PROJECT IS COMPLETED IN ACCORDANCE WITH THE
PLANS AND SPECIFICA TlONS AS STIPULA TED IN THE PERMIT APPROVAL CONDITIONS."
~;tt;.--{,j
Gregg Ha ll , Manager -Siting & Permitting 1
PRINT NAME & CONTRACTORS LICENSE NO . FinFf........,'--------------~~~W\NVVV;M;VVw..",.fi
FOR OFFICE USE ONL Y
A pPROVED I BY DATE PERMI T FEE COMMENTS
D ,SAPPROVED
Rev. 2016
PERM IT IS VALID FOR SI X MO NTHS FRO M DATE OF ISSUANCE , UNLESS OT HERWI SE NOTED .
City of South Miami
Public Works & Engineering Department
4795 SW 75th Avenue
Miami, FL 33155
Tel. (305) 403-2063 Fa x (305) 668-7208 THF CIT Y OF PI FASAN T I.I VING
PERMIT CONDITIONS
Date: 3/212017 Permit # 17-100000 ____ _
Company: Florida Power & Li9ht Name: _G_r_e.:;::9:::..9 _H_8_1I ________ _
We accept the conditions listed below (signature): ~/J~4 /~.
1. Permit for construction work shall be on project site at all times.
2. Permits are valid for a period of six months from the date of issuance. If work is not complete before
permit expiration (six months), a permit extension can be applied for, before the permit expires.
Otherwise, a new permit application will be required for work on the right of way to be performed.
A new permit application will be required if the permit expires . It is the sole responsibility of the
contractor to apply for an extension at the PW office .
3. All materials and labor under the project shall be in strict accordance with the requirements of the City of
South Miami, Miami-Dade County, and all other local, state, and national codes, where applicable.
4. All construction shall be performed in a safe manner in accordance with the rules and regulations of the
Occupational Safety and Health Administration (OSHA).
5. Contract or shall notify the City of South Miami Public Works Department (CSM PW) forty-eight hours (48)
prior to commencing work.
6 . Contractor shall notify any affected property owners prior the permitted work starts.
a. In case when the work will disturb the traffic on the only accessing roadway, contractor is to
notify all property owners who have properties in between the access points on that roadway .
b. Egress and ingress shall remain accessible to each property .
7. During construction, the project site and all adjacent areas shall be secured and maintained in a neat and
clean manner.
8 . Traffic shall be maintained in accordance with Florida Department ofTransportation (FOOT) Maintenance
of Traffic (MOT) standards, Miami-Dade County standards, Manual of Uniform Traffic Control Devices
(MUTCD) and any additional requirements by the CSM PW and Police Department.
a. If a full or partial road closure is required, a MOT must be submitted and approved by CSM PW
and City of South Miami Police Department (CSM PD). No street shall be closed without written
authorization .
b. Any pedestrian MOT shall be per FOOT Standard Inde x 660 .
c. Applicant shall coordinate the schedule of the MOT with the CSM PD . Chief of Police and/or CSM
PD may be reached at 305-663-6301. Any directions by CSM PO, before, during and/or after the
work is being performed, shall be followed by the applicant, workers and/or any other i nvolved
party.
City of South Miami
Public Works & Engineering Department
4795 5W 75th Avenue
Miami, FL 33155
Tel. (305) 403-2063 Fa x (305) 668-7208 THf CITY OF PLFASANT liV ING
d . Access for local traffic shall be maintained at all times .
9. If the work will obstruct parking of vehicles at the street paid parking spaces, the applican t shall pay the
daily parking fees for each of the obstructed paid street parkin g spaces .
10. No material or equipment shall be staged in the public R/W overnight unless specifically authorized by the
Department.
11. All pavement open-cut during permitted work shall be temporarily resto r ed with asphalt or steel plates at
the end of each workday. NO TRENCHES OR PITS SHALL BE LEFT OPEN OVERNIGHT. Permanent asphalt
restoration shall occur within 14 days of open-cut.
12. Contractor shall conduct daily dust control and implement storm water erosion and sediment control
measures for pollution prevention.
13. Any damage to private property shall be restored to its original condition or better and as accepted by the
owner.
14. Disturbed areas shall be restored to equal or better condition than they were before the work started.
The restoration shall include the following :
a. Road/pavement areas shall be restored at least 5' from the edges of disturbed areas and as per
the City of South Miami Standard Details for Pavement Restoration.
b. Sidewalk panels shall be replaced, i.e ., the sidewalk shall be restored in full width .
c. Landscaped areas, including and not limited to grass, sod, shrubs and trees replacement, shall be
fully restored.
d . For intersections with pavers, the full intersection shall be restored regardless ofthe size ofthe
disturbed area .
15. If all restoration work is not performed within 30 days of work completion, the CSM PW may restore the
work area and charge the applicant for the cost of restoration plus a minimum of 15% for administrative
fee and any additional incidental fees.
16. All utility location markings within the right-of-way shall be removed before project closeout.
17 . All rims of manholes and water valves shall be at grade when repair is finished .
18. Work is not permitted on Saturdays, Sundays and Holidays . Work is only allowed from 8 am to 5 pm ,
unless otherwise authorized .
19 . Call 811 prior to diggi ng . For Sunshine State One Call of Florida, call 1-800-432-4770; to make an online
request for utilities to be marked, go to www .callsunshine .com or
http://www 2 .callsunshine .com/irthinternet/welcome.asp .
11
R-SOUTH MIAMI 138 kV TRANSMISSION LINE
Aoh:,,..,,,to 6 Structures and remove 1 at SW 62"d Avenue
10-1000000152
[lliEET!}clO
t
r
l ~
CUTLER-SOUTH MIAMI 138 kV TRANSMISSION LINE
Relocate 6 Structures and remove 1 at SW 62nd Avenue
10-roo . 0 01527.2
Section A-A (Existing)
Structures 81A18, 81A18A, 81A19, 81A19A 81A20, 81A2l, 81A22
lii+w.§i§.iiii j
Median
"22'
6'
EOP
Notes:
1.-All new poles will be located back face of the pole against the back of the sidewal k.
2.-Utilities will be notified prior to start construction.
RW
3.-New SPC poles w il l be located within 10 feet of existing squa re concrete poles, except for Str, 81A20, which will be moved 25 feet to South ,
4 ,-Structure 81A19A will be completely r emoved. A new pole will be set In the back of the sidewalk to transfer Distribution facilities ,
5.-Existing street light at Structure 81A18A will be also transferred to the new transmission pole,
G.-Call 305-234 -2111 for final inspection. If lane closures are required, notify the South Miami Police and Public Works Departments.
7.-Call Miami Dade Fire Department 48 hours prior to construction starts.
MOT: 660 and a signed and sealed custom MOT plan Is In process for the whole relocation project.
o 69kV
o 230kV
Section A-A (Proposed)
Structures 81A18, 81A18A, 81A19, 81A20, 81A21, 81A22
sldewalk ~ IM*-+I§iiiiil
Median
.' ~ ______ ~-U~· ________ ~.~+ _______ ~-Z~Z_· _______ ~ .' 6'
-------EOP RW
13 , TWP . 54 S., RGE . 40 E. FPL 10-TOO000015275
CoU" W FOEP FOOT FFA line: Nllme: Cutler-South Mllml13e kV
RR XI". DR .Dht. CaE County : Miami Dade o 115kV 138 kV Scope: Relocate 6 Structuru Ind remove 1 to meet ADA ilt SW 62 .... Avenue
o SOOkV
Dra wn by: Herlberto J Alvarel Date: oclober 2015 o CONTAMINATION Scale: Pro rtlon.1 Owg No. SHEET: B of 8