CITY OF SOUTH MIAMI
OFFICE OF THE CITY MANAGER
INTER-OFFICE MEMORANDUM
The Honorable Mayor & Members of the City Commission
Steven Alexander, City Manager
Kelly Barket Jr., Director of Public Works
Agenda Item No.:ll February 16, 2016
A Resolution authorizing the City Manager to purchase an electronic fuel
monitoring board from Petroleum Testing Services Inc.
The current electronic fuel monitoring board console for the Police fuel pumps
at City Hall has failed. The system depends on a functioning console for all fuel
monitoring requirements.
A monitoring system is required for all regulatory certifications. The system will
provide several major safety measurements, including but not limited to, leak
detection, pressure measurements, dispensing fuel levels and tank
contamination.
PSR Inc. will supply and install one functional complete VeedeRoot TLS-350 plus
monitoring system with integrated printer and module and all applicable
compliance monitoring sensors, wiring, materials, conduit, tank connections,
labor and Final Annual Certification as indicated in option #3 on the attached
proposal.
The monitoring system to be installed is compatible with the current
operational system in use by the City. PSR Inc. was the lowest and most
responsive bidder and met all requirements of the scope needed for services.
PSR Inc. $6,840.00
Fred Rice LLC. $8,986.00
Branching Out, Inc. $9,850.00
$6,840.00
Account No.: 001.1710.519.4670 has a current balance of $49,122
Quote I. PSR Inc.
Quote 2. Fred Rice LLC.
Quote 3. Branching Out, Inc.
1 RESOLUTION NO.: ___ ~ _____ _
2
3 A Resolution authorizing the City Manager to purchase an electronic fuel
4 monitoring board from Petroleum Testing Services Inc.
5
6 WHEREAS, the current .electronic fuel monitoring board console at City Hall has failed.
7 The system depends on a functioning console for all fuel monitoring requirements; and
8
9 WHEREAS, a monitoring system is required for all regulatory certifications. The system
10 will provide several major safety measurements, including but not limited to, leak detection,
11 pressure measurements, dispensing fuel levels and tank contamination; and
12
13 WHEREAS, the City obtained 3 quotes for the purchase of an electronic fuel monitoring
14 board; and
15
16 WHEREAS, PSR Inc. was the lowest & most responsive bidder; and
17
18 NOW, THEREFORE, BE IT RESOLVED THE MAYOR AND CITY COMMISSION OF THE CITY
19 OF SOUTH MIAMI, FLORIDA:
20
21 Section 1. The City Manager is authorized to expend $6,840 with PSR Inc. for the
22 purchase of an electronic fuel monitoring board, charged to account number 001-1710-519-
23 4670 (Repair of Grounds & Structures) with a current balance of $49,122 . •
24
25 Section 2. Severability. If any section, clause, sentence, or phrase of this resolution is
26 for any reason held invalid or unconstitutional by a court of competent jurisdiction, this holding
27 shall not affect the validity of the remaining portions of this resolution.
28
29 Section 3. Effective Date: This resolution shall take effect immediately upon
30 enactment.
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
PASSED AND ENACTED this __ day of ____ --', 2016.
ATIEST:
CITY CLERK
READ AND APPROVED AS TO FORM,
LANGUAGE, LEGALITY AND
EXECUTION THEREOF
CITY ATIORNEY
APPROVED:
MAYOR
COMMISSION VOTE:
Mayor Stoddard:
Vice Mayor Harris:
Commissioner Liebman:
Commissioner Edmond:
Commissioner Welsh:
VEEDER-ROOT
~/ ......
I I' I rI,'NC PetROLEUM TESTING_ SeRVll:ES
PH-954-553-3675 FX-954-572-0806
marty@psrtesting.net
Proposal
Date: 2/1/2016
Location: City of South Miami
Attn: Eddy Torres.
TASK) Repair / Replace non functional OPW Tank monitoring system.
PSR Inc. will supply / repair / or replace applicable elements to the existing OPW monitoring system depending
on the preferred proposal options listed below. All new materials and parts will be warranted for one year upon
successful installation or repair and proper functionality.
• 1) Replace OPW console with a *functional unit. Console to include all capabilities,
components, software and programming. Upon successful installation, determine, if any,
remaining issues with the system, additional costs may apply. This unit will be warranted for one
year from time of installation. Cost for this Task will be $3,216.00
• 2) Supply and replace one OPW EECO 1500 Console main board. Upon successful installation,
determine, if any, remaining issues with monitoring system. Additional costs may apply.
Cost for this Task will be $1,840.00
• 3) Supply and install one *functional, complete VeedeRoot TLS-350 Plus Monitoring system
with integrated printer and modules, to include, Tank Gauging Probe, all applicable compliance
monitoring sensors (annular space and sumps), wiring, materials, conduit, tank connections,
labor, and Final Annual certification. Complete Task warranted for one year from installation
time. Cost for this Task will be $6,840.00
* Represents that unites) is used and is covered with the one year manufacturer warranty.
Thank you.
Proposal/Task Acceptance: ___________ _
Print name:
Date:
IN
M. Sweet (Marty)
Compliance Specialist
Fred Rice LLC.
6607 Don/on Rd.
FT. Pierce FL 34951
772.464.7177
Estimate: #10094-16
BILL TO:
City of South Miami.
4795 SW 75 th Ave
S. Miami FL 33155
Attn. Eddie T.
Date 1/4/2016
SHIP TO:
City of South Miami
Same
Description: Install Veeder-Root TLS-350 Monitoring system.
1) Provide new VeederRoot TLS-350 system complete to include all applicable
probes, sensors, materials, and installation.
-VeederRoot TLS-350 Console with printer
-1 Magnetostrictive Tank Probe
-2 Compliance Sensors
-1 Conduit, connections, materials
-1 Shipping
-1 Tax
Sub-total
Total
Estimated project duration will be two days.
$4,600.00
$1,800.00
$630.00
$1,840.00
$116.00
N/A
$8,986.00
Approval signature. X. _____________ Date ______ _
Print name .x _______________ _
23300 S.W.134 Avenue
Miami, Florida 33032
Ph: 305 258-8101 Branching Out, Inc.
EB6740
PCC055725
ECC001470
CGC006150
Fax:305 258-3812 Environmental Engineering construction CFC057075
January 20, 2015
Mr. Eddie Torres
City of South Miami
etorres@southmiamifl.gov
305~519-6785
RE: Proposal for Electrical construction service
Dear Mr. Torres:
In accordance with your request" this proposal for professional
construction services is submitted for your consideration and
approval.
I PURPOSE OF AGREEMENT / PROJECT DESCRIPTION
Tasks:
Contractor Shall:
.:t. Provide necessary labor and materials to Install New
VEEDER ROOT,TMS 300 Console.
2. Provide and install new interstitial leak detection and
level probes in tank as required.
3. Land all leads and provide a complete working package.
Lump Sum Price . . " t (, '.', • . ,. . . . .. ; .. $9, 850.00
Should you have any questions or require additional information,
please contact me at (305) 258-8101.