13-1163-006WPIRK. PHASES:
A THE WORK SHALL BE CONDUCTED IN TWO SUB- PHASES IN THE FOLLOWING ORDER PHASE I WILL BEGIN UPON
ISSUANCE OF NOTICE TO PROCEED. PHASE 2 ON -SITE WORK MAY BEGIN UPON SUBSTANTIAL COMPLETION OF
PHASE 1. ALL WORK TO BE COMPLETED UPON COMPLETION OF PHASE 2.
IA PHASE 1: INSTALLATION OF PHASE 1 CONSTRUCTION BARRIERS, DEMOLITION OF INTERIOR
PARTITIONS, PARTIAL CONSTRUCTION OF PERMANENT PARTITION, RENOVATION OF EXISTING WOMEN'S
RESTROOM, INSTALLATION OF NEW EWC, WAITING ROOM CASEWORK 4 FINISHES.
a. THE WORK OF PHASE i MAY BE PERFORMED DURING OFF -PEAK HOURS. (SCHEDULE WORK AT
NIGHT)
R) UTILITY SHUTDOWNS, NOISY OPERATIONS (SUCH AS SAW CUTTING) ARE CONSIDERED TO
ADVERSELY AFFECT THE OPERATIONS OF THE EXISTING FACILITY AND SHALL BE SCHEDULED DURING
TIMES WHEN THE FACILITY IS NOT OPERATIONAL AS NOTED HEREIN FOR UTILITY SHUTDOWNS.
b. UTILITY SHUTDOWNS TO BE SCHEDULED WITH THE HOSPITAL STAFF 4 COORDINATED WITH AND
APPROVED BY THE SMH PROJECT MANAGER IN ADVANCE IN ACCORDANCE WITH BHSF POLICY.
15. PHASE 1: INSTALLATION OF PHASE 2 CONSTRUCTION BARRIERS, DEMOLITION OF INTERIOR
PARTITIONS, CONSTRUCTION OF PERMANENT PARTITION, RENOVATION OF EXISTING MEN'S RESTROOM,
WAITING ROOM FINISHES.
a. THE WORK OF PHASE I MAY BE PERFORMED DURING OFF -PEAK HOURS. (SCHEDULE WORK AT
NIGHT)
I) UTILITY SHUTDOWNS, NOISY OPERATIONS (SUCH AS SAW CUTTING) ARE CONSIDERED TO
ADVERSELY AFFECT THE OPERATIONS OF THE EXISTING FACILITY AND SHALL BE SCHEDULED DURING
TIMES WHEN THE FACILITY IS NOT OPERATIONAL AS NOTED HEREIN FOR UTILITY SHUTDOWNS.
b. UTILITY SHUTDOWNS TO BE SCHEDULED WITH THE HOSPITAL STAFF 4 COORDINATED WITH AND
APPROVED BY THE SMH PROJECT MANAGER IN ADVANCE IN ACCORDANCE WITH BHSF POLICY.
1. FOR ALL PHASES: STRICTLY FOLLOW ICRA PROCEDURES TO PREVENT CONTAMINATION OF
SYSTEMS AND TO FULLY RESTORE SANITARY AND CLEAN CONDITIONS AT THE END OF THE WORK PERIOD.
a. WORK IN PUBLIC AREAS NOT WITHIN THE PROJECT LIMITS TO BE SCHEDULED TO ALLOW FOR
OWNER AND PUBLIC OPERATIONS TO CONTINUE WITHOUT DISRUPTION.
B. BEFORE COMMENCING WORK OF EACH PHASE, SUBMIT A SCHEDULE SHOWING THE SEQUENCE, COMMENCEMENT
AND COMPLETION DATES, AND MOVE -OUT AND -IN DATES OF OWNER'S PERSONNEL FOR ALL PHASES OF THE
WORK.
PHASING NOTES:
1. ALL AREAS DISTURBED BY CONSTRUCTION SHALL BE RESTORED TO THEIR ORIGINAL CONDITION.
2. PHASE SEQUENCE OF WORK AND TAKE NECESSARY MEASURES TO MAINTAIN FACILITY FUNCTIONALITY
AND TO PROVIDE FOR THE SAFETY OF PERSONS AND PROPERTY AT THE FACILITY.
3. CONTINUOUSLY MAINTAIN ALL NECESSARY UTILITIES TO THE OCCUPIED FACILITIES DURING
CONSTRUCTION
4. ALL EXISTING EXITS AND EXISTING FIRE PROTECTION SHALL BE CONTINUOUSLY MAINTAINED. OR IN
LIEU THEREOF, OTHER MEASURES SHALL BE TAKEN WHICH PROVIDE EQUIVALENT SAFETY.
4a. ALL TEMPORARY DOORS TO BE S.C1U. 'C- LABEL" (l -HOUR FIRE RATED) W/ SELF - CLOSER LATCH, AND
LOCKSET)
5. PROVIDE TEMPORARY CONSTRUCTION FENCE OR WALLS AROUND CONSTRUCTION AREAS AND
CONTRACTOR'S STAGING AREA PROVISIONS SHALL BE MADE TO MAINTAIN ALL REQUIRED FIRE EXITS
FROM THE EXISTING FACILITY.
6. EACH CONSTRUCTION PHASE SHALL INCLUDE ALL WORK WITHIN THE CONSTRUCTION AREA
BOUNDARIES AND ALL RELATED SITE AND UTILITY WORK REQUIRED FOR THAT PARTICULAR PHASE
UNLESS NOTED OTHERWISE.
1. EXCEPT FOR THOSE SPACES WITHIN WORK AREA, (WHICH WILL BE VACATED DURING CONSTRUCTION
ACTIVITIES EXCEPT AS INDICATED OTHERWISE), THE FACILITY SHALL BE MAINTAINED FIT FOR
OCCUPANCY AND BE FUNCTIONAL AT ALL TIMES, TOGETHER WITH ALL ELECTRICAL, HVAC
MECHANICAL, PLUMBING, SAFETY, AND COMMUNICATION SYSTEMS.
8. COORDINATE AND SCHEDULE OWNER PERSONNEL FOR RELOCATION AND STORAGE OF OWNER'S
MATERIALS, SUPPLIES, EQUIPMENT, AND FURNITURE AS NECESSARY TO ALLOW CONSTRICTION
OPERATIONS OF EACH WORK AREA
3 WORK AT ANY GIVEN AREA SHALL NOT COMMENCE UNTIL ALL REQUIRED PRODUCTS, MATERIALS, AND
EQUIPMENT ARE AVAILABLE, OR SCHEDULED TO BE AVAILABLE, AS NECESSARY TO ALLOW
COMPLETION OF THE WORK IN A TIMELY MANNER AND WITHOUT UNNECESSARY DELAYS. THIS IS
REQUIRED IN ORDER TO MINIMIZE INTERRUPTION OF ACTIVITIES AND USE OF THE FACILITY.
10. UPON COMPLETION OF WORK AT EACH PHASE, REQUIRED ACCEPTANCE INSPECTIONS AND PUNCH LIST
INSPECTIONS SHALL BE PERFORMED AND WORK DETERMINED TO BE SUBSTANTIALLY COMPLETED
PRIOR TO COMMENCEMENT OF WORK AT THE SUBSEQUENT PHASE.
IL PUNCH LIST WORK FOR EACH PHASE SHALL BE PEED IMMEDIATELY UPON SUBSTANTIAL
COMPLETION IN A PER PHASE BASIS AND WITHOUT IMPACTING OWNER'S OCCUPANCY AND USE OF
6PACES WITHIN SUBJECT PHASE.
12. WHEN APPROPRIATE DURING DEMOLITION, PROVIDE WATER MIST DAMPING OF ITEMS TO BE
DEMOLISHED AS NECESSARY FOR DUST AND AIRBORNE PARTICLE CONTROL.
13. MAINTAIN ACCESS TO CHILLERS, GENERATOR SWITCH GEAR, F.P.L. AT ALL TIME.
14. AVOID CUTTING EXISTING PIPE, CONDUIT OR DUCTWORK SERVING BUILDING AND SCHEDULED TO BE
REMOVED OR RELOCATED UNTIL PROVISIONS HAVE BEEN MADE TO BYPASS THE SYSTEM.
15. COORDINATE SHUTDOWNS WITH OWNER'S PROJECT MANAGER PROVIDE 10 DAYS NOTICE MINIMUM..
-NOTE: UIHERECONCEALED SPACE ABOVE CEILING IS CONTINUOUS WITH NON - PROJECT AREAS,
PROVIDE CONTINUOUS DUST BARRIER - 6 MIL. POLY DUST BARRIER FULLY SEALED AT JOINTS
AND PERIMETER WITH FIRE RETARDANT DUCT TAPE - SEE DETAIL BELOW (CONTRACTOR TO
REMOVE ALL TRACES OF BARRIER UPON COMPLETION OF WORK. CONTRACTOR TO PATCH AND
REPAIR AREAS OF WALL, CEILING, AND FLOORING DISTURBED BY BARRIER TO MATCH EXISTING)
SLAB /STRUCTURE ABOVE
CONSTRUCTION
SIDE
+-DOORS 4 WALL -
I HOUR CONSTRUCTION,
HARDWARE AND FINISH TO MATCH
EXISTING WAITING ROOM DOORS
"PAINT TEMP. WALL TO MATCH
EXISTING WAITING ROOM FINISHES
EXISTING TILE FLOOR TO REMAIN
- EVERY ATTEMPT SHALL BE
MADE TO INSTALL TEMP.
BARRIER WITHOUT DAMAGING
EXISTING TILE FLOOR
FASTEN BARRIER THROUGH
NEAREST EXISTING TILE GROUT LINE
DUCT TAPE /
AT PERIMETER
(p MIL. POLY
DUST BARRIER
FULLY SEALED
AT JOINTS —,,,,
EXIST.
CEILING –,
2 X 2 FIRE
RETARDANT WD.
CONCEALED
CEILING
SPACE
EXIST.
CEILING p<
EXIST. OR WAITING ROOM
P
TEM. WALL SIDE
TYPE X TYPE X
GWB GWBss
SOUND
INSULATIO
PROVIDE
WALL BASE TO
MATG -I EXIST.
a-
S-
10-
12-
13-
14-
15-
Iro -
STANDARD PRECAUTIONS:
17.1 GLOVES, IMPERVIOUS GOWNS, GOGGLES, MASK AND SIMILAR
PROTECTIVE GEAR MUST BE USED WHEN POTENTIAL CONTACT WITH
PATIENT'S BLOOD OR OTHER FLUID IS ANTICIPATED.
1'12 REPORT TO YOUR IMMEDIATE SUPERVISOR AND EMPLOYEE HEALTH
SERVICES IF YOU HAVE ANY OF THE FOLLOWING:
A - GENERALIZED RASHES OR SKIN LESIONS THAT ARE VESICULAR
(WITH FLUID), PUSTULAR (RAISED) OR WEEPING.
B - JAUNDICE (YELLOW EYES)
C - COUGH THAT PERSISTS FOR MORE THAN 2 WEEKS.
D - ACUTE GASTROINTESTINAL ILLNESS (3 LOOSE STOOLS IN 24 HRS.
WITH OR WITHOUT ASSOCIATED SYMPTOMS SUCH AS FEVER, NAUSEA
AND ABDOMINAL PAIN).
E - HOSPITALIZATION DUE TO AN INFECTIOUS DISEASE.
G - EXPOSED TO A COMMUNICABLE DISEASE IN THE COMMUNITY (I.E.
CHICKENPDX, MEASLES, MUMPS, RUBELLA, PULMONARY
TUBERCULOSIS).
ATTIRE:
16.1 HEAVY BOOTS, IMPERVIOUS OVERALLS, FACESHIELDS, HEAVY
DUTY GLOVES MUST BE WORK WHEN EXPOSED TO GROSS
CONTAMINATED WASTE (I.E. DUMPSTERS, BROKEN SEWAGE LINES).
182 A CONE MASK MUST BE WORK WHEN CHANGING AN AIR
CONDITIONING FILTER
183 HANDS MUST BE WASHED AFTER COMPLETING WORK INVOLVING
PLUMBING.
PLACE SIGNAGE TO IDENTIFY CONSTRUCTION SITE AND CONSTRUCTION
TRAFFIC ROUTE.
SEE SPECIFICATION SECTION FOR OTHER APPLICABLE PROVISIONS.
ENVIRONMENTAL SERVICES DEPARTMENT. INFECTION CONTROL GUIDELINES:
ERECT TEMPORARY FIRE RETARDANT PLYWOOD PARTITIONS AT EXTERIOR (UPON COMPLETION OF PROJECT)
TO MAINTAIN A WATERPROOF ENVIRONMENT DURING CONSTRUCTION
INFECTION CONTROL GUIDELINES: CLASS III (DURING CONSTRUCTION)
1 -
ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT 1i-
CONTAMINATION OF DUCT SYSTEM. (SEE M -DWGS)
2-
COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK, PLYWOOD, PLASTIC, TO
DURING DEMOLITION AND CONSTRICTION ACTIVITIES.
SEAL AREA FROM NON -WORK AREA OR IMPLEMENT CONTROL CUBE METHOD
Scale: N.T.S.
(CART WITH PLASTIC COVERING AND SEALED CONNECTION TO WORK SITE
TRAFFIC MUST BE DIRECTED FROM CONSTRUCTION AREAS AWAY FROM
WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT) BEFORE CONSTRUCTION
PATIENT CARE AREAS TO LIMIT DUST DISPERSION, ENTRY OF CONTAMINATED
BEGINS. AIRTIGHT BARRIERS OF PLASTIC OR WALLBOARD MUST BE
AIR OR TRACKING OF DUST INTO PATIENT CARE AREA
CONSTRUCTED PRIOR TO CONSTRUCTION/RENOVATION BETWEEN PATIENT
CLEANING OF VENTILATION SYSTEM DURING AND AFTER CONSTRUCTION MUST
CARE AND CONSTRUCTION AREAS TO PREVENT DUST FROM ENTERING
OCCUR IF IT GETS CONTAMINATED.
PATIENT CARE ALAS.
RENOVATED /CONSTRUCTION AREA MUST BE CLEANED PRIOR TO PATIENT
A) DOORS MUST BE KEPT CLOSED
RE- ENTERING AREA
B) DUST AT CONSTRUCTION SITE DOORWAYS 4 ALONG CONSTRUCTION
REPORT HAZARDS TO THE APPROPRIATE DEPARTMENT
ROUTE MUST BE CLEANED INTERMITTENTLY AND ROUTINELY.
C) MATS MUST BE PLACED AT EXIT OF CONSTRUCTION FOR WIPING FEET.
3-
MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA
EQUIPPED AIR FILTRATION UNITS. MAINTAIN NEGATIVE PRESSURE
IF A SIGN STATING "AIRBORNE" OR "DROPLET" PRECAUTION IS POSTED ON
DIFFERENTIAL OF 0.01" WAG. IN RELATION TO ADJOINING OCCUPIED SPACES. 15-
A PATIENT DOOR WEAR THE MASK AVAILABLE BY THE DOOR BEFORE
CONTINUITY OF DIFFERENTIAL PRESSURE SHALL BE DOCUMENTED BY
ENTERING THE ROOM. DISCARD THE MASK AFTER LEAVING THE ROOM AND
CONTINUOUS MONITORING AND RECORDING EQUIPMENT. PROVIDE HVAC
CLOSE DOOR
TEST 4 BALANCE REPORT INDICATING COMPLIANCE PRIOR TO
WASH HANDS:
COMMENCEMENT OF WORK (SEE MECH. DWGS FOR ADDITIONAL NOTES)
4-
CONTAIN CONSTRUCTION WASTE IN TIGHTLY COVERED CONTAINERS BEFORE
WHEN CHANGING GLOVES
TRANSPORTING.
5-
COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS
,ANY TIME HANDS ARE SOILED
SOLID LID.
19-
6 -
SEAL HOLES, PIPES, CONDUITS AND PUNCTURES APPROPRIATELY.
7-
DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT 20-
16 INSPECTED BY THE OWNER'S SAFETY DEPARTMENT AND INFECTION
CONTROL DEPARTMENT AND THOROUGHLY CLEANED BY THE OWNER'S
a-
S-
10-
12-
13-
14-
15-
Iro -
STANDARD PRECAUTIONS:
17.1 GLOVES, IMPERVIOUS GOWNS, GOGGLES, MASK AND SIMILAR
PROTECTIVE GEAR MUST BE USED WHEN POTENTIAL CONTACT WITH
PATIENT'S BLOOD OR OTHER FLUID IS ANTICIPATED.
1'12 REPORT TO YOUR IMMEDIATE SUPERVISOR AND EMPLOYEE HEALTH
SERVICES IF YOU HAVE ANY OF THE FOLLOWING:
A - GENERALIZED RASHES OR SKIN LESIONS THAT ARE VESICULAR
(WITH FLUID), PUSTULAR (RAISED) OR WEEPING.
B - JAUNDICE (YELLOW EYES)
C - COUGH THAT PERSISTS FOR MORE THAN 2 WEEKS.
D - ACUTE GASTROINTESTINAL ILLNESS (3 LOOSE STOOLS IN 24 HRS.
WITH OR WITHOUT ASSOCIATED SYMPTOMS SUCH AS FEVER, NAUSEA
AND ABDOMINAL PAIN).
E - HOSPITALIZATION DUE TO AN INFECTIOUS DISEASE.
G - EXPOSED TO A COMMUNICABLE DISEASE IN THE COMMUNITY (I.E.
CHICKENPDX, MEASLES, MUMPS, RUBELLA, PULMONARY
TUBERCULOSIS).
ATTIRE:
16.1 HEAVY BOOTS, IMPERVIOUS OVERALLS, FACESHIELDS, HEAVY
DUTY GLOVES MUST BE WORK WHEN EXPOSED TO GROSS
CONTAMINATED WASTE (I.E. DUMPSTERS, BROKEN SEWAGE LINES).
182 A CONE MASK MUST BE WORK WHEN CHANGING AN AIR
CONDITIONING FILTER
183 HANDS MUST BE WASHED AFTER COMPLETING WORK INVOLVING
PLUMBING.
PLACE SIGNAGE TO IDENTIFY CONSTRUCTION SITE AND CONSTRUCTION
TRAFFIC ROUTE.
SEE SPECIFICATION SECTION FOR OTHER APPLICABLE PROVISIONS.
ENVIRONMENTAL SERVICES DEPARTMENT. INFECTION CONTROL GUIDELINES:
ERECT TEMPORARY FIRE RETARDANT PLYWOOD PARTITIONS AT EXTERIOR (UPON COMPLETION OF PROJECT)
TO MAINTAIN A WATERPROOF ENVIRONMENT DURING CONSTRUCTION
Temporary Barrier Detail
ACTIVITIES.
Proposed Construction / Patient / Staff Routing Plan
r 1
ALL AIR VENTS ARE TO BE BY- PASSSED TO PREVENT CONTAMINATION
Plan
DURING DEMOLITION AND CONSTRICTION ACTIVITIES.
PH•1.01
Scale: N.T.S.
2-
TRAFFIC MUST BE DIRECTED FROM CONSTRUCTION AREAS AWAY FROM
PH•1.09
PATIENT CARE AREAS TO LIMIT DUST DISPERSION, ENTRY OF CONTAMINATED
3-
AIR OR TRACKING OF DUST INTO PATIENT CARE AREA
L
CLEANING OF VENTILATION SYSTEM DURING AND AFTER CONSTRUCTION MUST
4-
OCCUR IF IT GETS CONTAMINATED.
RENOVATED /CONSTRUCTION AREA MUST BE CLEANED PRIOR TO PATIENT
5-
RE- ENTERING AREA
REPORT HAZARDS TO THE APPROPRIATE DEPARTMENT
rc, -
ALWAYS READ THE SIGNS POSTED ON DOOR OF A PATIENT'S ROOM
IF A SIGN STATING "AIRBORNE" OR "DROPLET" PRECAUTION IS POSTED ON
A PATIENT DOOR WEAR THE MASK AVAILABLE BY THE DOOR BEFORE
ENTERING THE ROOM. DISCARD THE MASK AFTER LEAVING THE ROOM AND
S- F
CLOSE DOOR
WASH HANDS:
BEFORE AND AFTER PATIENT AREA CONTACT/EXPOSURE
WHEN CHANGING GLOVES
AFTER USING THE RESTROOM
,ANY TIME HANDS ARE SOILED
Plan Legend
CONSTRUCTION — LINE OF PROPOSED
CONSTRUCTION ROUTE
PATIENT LINE OF PROPOSED
PATIENT ROUTE
— PHYSICIA
PATIENT
DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED
PROJECT 15 THOROUGHLY INSPECTED BY OWNER'S STAFF.
VACUUM WORK AREA WITH I4EPA FILTERED VACUUMS
WET MOP / WIPE EXPOSED SURFACES WITH APPROPRIATELY
ABELED AND BHSF APPROVED HOSPITAL DISINFECTANT.
CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY
COVERED CONTANERS.
COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING
UNLESS SOLID LID.
REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS
BEING PERFORMED.
REMOVE BARRIER MATERIAL CAREFULLY TO MINIMIZE SPREADING
OF DIRT AND DEBRIS ASSOCIATED WITH CONSTRUCTION.
INAL CLEANING BY ENVIRONMENTAL SERVICES PRIOR TO
OCCUPANCY.
Phasing Plan Legend
— • - , — PROVIDE TEMPORARY
•— • • -- ENCLOSURE 4 PLENUM
PROTECTION*
(SEE DTL 2/PH -1.01)
SCOPE OF WORK FOR
SPECIFIED PHASE
WALK-OFF MAT (STICKY)
AT CONSTRUCTION
ENTRANCE
RE
a
• - Plan
' ,
2
�1' , I
4
Temporary Barrier Detail
3
Proposed Construction / Patient / Staff Routing Plan
r 1
Phase 1
Plan
PH•1.01
Scale: N.T.S.
PH•1.01
Scale: 3/32 " =1' -0"
PH•1.09
Scale: 1/4
" =1' -d"