Loading...
10-818-033c 0 L E a 0 0 N 0 0 N N E 0 a� E LL LL Z U Li C a_ a, co N N 0 N N Fv. 0 J CL F-- a 0 SPRINKLER NOTES 1. ALL FIRE PROTECTION SYSTEM SHALL BE IN COMPLIANCE WITH THE STATE AND LOCAL FIRE CODES AND ORDINANCES AND AS PER NFPA 13 - 2002 AND NFPA 14 - 2003 EDITION REQUIREMENTS. 2. MAKE ALL OFFSETS REQUIRED AS PER JOB CONDITIONS. 3. CONTRACTOR TO PROVIDE AND TURN OVER TO THE OWNER AT LEAST (6) SPARE SPRINKLERS OF SAME TYPE AND TEMPERATURE RATING BEING INSTALLED INSIDE OF SPARE SPRINKLER CABINETS. COORDINATE LOCATION WITH OWNER. 4. CONTRACTOR SHALL FIELD VERIFY AND COORDINATE SPRINKLER HEAD LOCATIONS WITH SOFFITS AND ANY CEILING OBSTRUCTIONS PER NFPA 13. 5. ALL SPRINKLER HEADS SHALL BE CENTERED AND PRESENT A NEAT AND BALANCED CEILING PATTERN UNLESS SHOWN OTHERWISE. 6. PROVIDE AND MAINTAIN A MINIMUM CLEARANCE OF 18' BETWEEN THE BOTTOM OF THE SPRINKLER DEFLECTOR AND THE TOP OF STORAGE, FILE, SHELVING, ETC. 7. CONTRACTOR SHALL FIELD VERIFY LOCATION AND QUANTITY OF ALL CEILING MOUNTED DEVICES INCLUDING SMOKE DETECTORS TO BE REMOVED DURING CONSTRUCTION TO INSTALL SPRINKLER PIPING. EXISTING EQUIPMENT AND FIXTURES SHALL BE REPAIRED TO ORIGINAL OPERATION OR REPLACED SHOULD THEY BE DAMAGED DURING CONSTRUCTION. 8. SCHEDULE 5 PIPING AND FLEXIBLE SPRINKLER HEAD DROPS ARE NOT APPROVED OR ACCEPTED PRODUCTS. 9. CONTRACTOR SHALL COORDINATE WITH STRUCTURE AND OTHER TRADES BEFORE INSTALLING SPRINKLER WORK. 10. SPRINKLER HEAD RATED a 155 DEGREES F.,1 /Z ORIFICE WITH 5.6 K- FACTOR, QUICK RESPONSE UNLESS OTHERWISE NOTED. 11. INSTALL PIPING TIGHT TO STRUCTURE WHERE POSSIBLE. 12. SPRINKLER SYSTEM SHALL BE INSTALLED BY A STATE CERTIFIED FIRE PROTECTION CONTRACTOR. 13. PAINT RED ALL EXPOSED FIRE RISERS, PIPING, INSPECTORS TESTS ASSEMBLIES & DRAIN RISERS. 14. SPRINKLER PIPING SHALL BE UL LISTED THREADABLE THINWALL AND /OR ALLIED XL 1' THROUGH 3' AND SCHEDULE 10 BLACK STEEL ASTM /A.135, UL LISTED FOR PIPING 4' AND LARGER. ALL EXTERIOR SPRINKLER PIPING AND FITTINGS SHALL BE SCHEDULE 40 HOT DIPPED ZINC COATED GALVANIZED. SEE SPECIFICATIONS FOR MORE INFORMATION. 15. SYSTEM DESIGNED FOR LIGHT HAZARD OCCUPANCY AND ORDINARY HAZARD GROUP I OCCUPANCY IN ELECTRICAL, MECHANICAL, AND STORAGE ROOMS. 16. CONTRACTOR SHALL REMOVE EXISTING SPRINKLER HEADS AS SHOWN AND ADJUST PIPING TO NEW CEILING PATERN. 17. CONTRACTOR SHALL COORDINATE WITH ALL DISCIPLINES INVOLVED SO AS TO AVOID ANY PIPE ROUTING PROBLEMS. 18. EXISTING SERVICES INDICATED ON THESE DRAWINGS WERE DERIVED FROM EXISTING DRAWINGS AND LIMITED FIELD OBSERVATIONS. THESE DRAWINGS MAY NOT BE ALL INCLUSIVE OF SERVICES THAT EXIST IN THE PROJECT AREA. CONTRACTOR SHALL VERIFY SERVICES, LOCATION, TYPE AND SIZE PRIOR TO ANY CONSTRUCTION. ANY DEVIATIONS IMPACTING WORK SHOWN ON THESE DOCUMENTS SHALL BE REPORTED TO THE ARCHITECT FOR COORDINATION PRIOR TO CONSTRUCTION. 19• CONTRACTOR IS RESPONSIBLE FOR RELOCATING ALL EXISTING FIRE MAINS AND SPRINKLER PIPING TO FACILITATE THE INSTALLATION OF NEW ELECTRICAL, MECHANICAL AND PLUMBING SYSTEMS. THIS INCLUDES ALL CEILING SPACES, SHAFTS, WALLS, ETC. 20. CONTRACTOR SHALL RAISE ALL EXISTING SPRINKLER PIPING WITHIN SCOPE TIGHT TO STRUCTURE AND PROVIDE NEW FITTINGS THROUGHOUT. 21. PRESSURE TEST PIPING AT 200 PSIG FOR A MINIMUM OF TWO HOURS. IF LEAKS ARE FOUND THEN CONTRACTOR SHALL FIX LEAKS AND TEST AGAIN. CONTRACTOR SHALL ALSO PROVIDE ALLOWANCE IN BID FOR PRESSURE TESTING OF EXISTING PIPING SHOWN TO REMAIN AT 200 PSIG FOR A MINIMUM OF 2 HOURS. ALLOWANCE SHALL INCLUDE FIXING LEAKS AND RETESTING. 22. FIRE PROTECTION CONTRACTOR SHALL PREPARE A SET OF INSTALLATION SHOP DRAWINGS BASED ON PIPE SIZES SHOWN COORDINATED WITH ALL THE ENGINEERING DISCIPLINES AND FIRE PROTECTION PIPING. THESE SHOP DRAWINGS SHALL BE SUBMITTED TO SSR ENGINEERS FOR APPROVAL PRIOR TO FABRICATION, INSTALLATION OR SUBMITTAL TO BUILDING DEPARTMENT. ALSO, MATERIAL SUBMITTALS SHALL BE SUBMITTED FOR REVIEW AND APPROVAL PRIOR TO ANY INSTALLATION. 23, CONTRACTOR SHALL PROVIDE PROVISIONS FOR FLUSHING SPRINKLER PIPING PER NFPA 13, 8.14.16. SHOW LOCATIONS OF FLUSHING CONNECTIONS ON SPRINKLER SHOP DRAWINGS. 24. SEAL PENETRATIONS OF FIRE RATED WALLS AND FLOORS IN ACCORDANCE WITH U.L. FIRE RESISTANCE INDEX FOR THROUGH PENETRATION FIRE STOP SYSTEMS. COORDINATE REQUIREMENTS WITH ARCHITECTURAL PLANS AND SPECIFICATIONS. 25. ALL GROOVED AND SCREWED FITTING SHALL BE APPROVED BY AN ENGINEER WHO RESERVES THE RIGHT TO DISAPPROVE ANY FITTING. ALL FITTING TYPES SHALL BE FROM THE SAME MANUFACTURER. 26. VISIT THE SITE TO CHECK AND VERIFY ALL EXISTING CONDITIONS PRIOR TO BIDDING TO INSURE THE COORDINATION OF THE FIRE SERVICES WITH EXISTING CONDITIONS. 27. CUTTING OF STRUCTURAL AND /OR ARCHITECTURAL MEMBERS TO BE DONE ONLY WITH THE WRITTEN APPROVAL OF THE ARCHITECT AND STRUCTURAL ENGINEER. 28. SPRINKLER HEADS ARE TO BE COORDINATED WITH ALL CEILING DEVICES (LIGHTS, DIFFUSERS. ETC.) AND STRUCTURAL SYSTEM. 29. INDICATE CENTER TO CENTER DIMENSIONS AND /OR PIPE CUT LENGTHS AND NOMINAL PIPE DIAMETERS OF ALL PIPING ON SHOP DRAWINGS. 30. INDICATE PIPE TYPE, SCHEDULE OF WALL THICKNESS AND METHOD OF JOINING ON SHOP DRAWING. 31. PROVIDE A PERMANENTLY ATTACHED NAME TAG STATING THE REQUIRED DESIGN CRITERIA FOR EACH HYDRAULICALLY DESIGNED SYSTEM. 32. IMMEDIATELY NOTIFY THE ARCHITECT /ENGINEER OF ANY DISCREPANCIES FOUND BETWEEN THESE PLANS, OTHER ENGINEERING PLANS, THE ARCHITECTURAL PLANS AND /OR FIELD CONDITIONS PRIOR TO FINAL BID PRICE OR FINAL PERMITTING. 33. IN CASE OF DISPUTE OR DOUBT AS TO INTENT OF DRAWINGS OR SPECIFICATIONS, OBTAIN ARCHITECT /ENGINEER'S DECISION BEFORE PROCEEDING WITH WORK OR BID INVOLVED. FAILURE TO FOLLOW THIS INSTRUCTION SHALL CONSTITUTE LIABILITY FOR DAMAGE TO OTHER WORK AND FOR REMOVING AND REPAIRING DEFECTIVE OR MISLOCATED WORK IN PROPER MANNER. 34. BEFORE SUBMITTING PROPOSAL OR BID, EXAMINE ALL DRAWINGS AND SPECIFICATIONS RELATING TO THIS PROJECT, THE AMOUNT OF SPACE AVAILABLE FOR PIPING, EQUIPMENT AND CONNECTING SERVICES, THE SITE OF THE WORK, THE REQUIREMENTS TO CORRELATE THE FIRE PROTECTION WORK WITH THAT OF OTHER TRADES AND THE TIME SCHEDULE NECESSARY TO PERFORM THAT WORK. 35. ALL SPRINKLER HEADS MOUNTED IN CEILING SHALL BE LOCATED A MINIMUM OF 4' AWAY FROM ANY WALLS, CEILING HEIGHT CHANGES OR ANY OTHER VERTICAL INTERSECTING STRUCTURAL SURFACE. 36. PIPE SHALL BE REAMED AND CLEANED BEFORE ASSEMBLY, AND AFTER ASSEMBLY. THE ENTIRE PIPING SYSTEM SHALL BE FLUSHED CLEAN. 37. ALL PENETRATIONS OR OPENINGS FROM REMOVED PIPES THROUGH EXISTING BUILDING WALLS AND FLOORS SHALL BE SLEEVED AND /OR PATCHED TO MATCH ORIGINAL. SEE ARCHITECTURAL DRAWINGS FOR FINAL FINISHES. 38. CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE TO EXISTING PIPING OR EQUIPMENT DUE TO NEW CONSTRUCTION AND HE SHALL RESTORE EXISTING WORK TO ITS ORIGINAL CONDITION AT NO COST TO THE OWNER. 39. PROVIDE HANGERS ON ALL ARMOVERS OF 12' OR MORE IN LENGTH AND PER NFPA 13. 40. WARRANTY /GUARANTEE A. THE CONTRACTOR SHALL WARRANTY /GUARANTEE AND MAINTAIN THE STABILITY OF WORK AND MATERIALS AND KEEP SAME IN PERFECT REPAIR AND CONDITION FOR THE PERIOD OF ONE YEAR. B. DEFECTS OF ANY KIND DUE TO FAULTY WORK OR MATERIALS, APPEARING DURING THE ABOVE MENTIONED PERIOD, MUST BE IMMEDIATELY REPAIRED BY THE CONTRACTOR AT HIS OWN EXPENSE TO THE ENTIRE SATISFACTION OF THE OWNER AND ENGINEER. SUCH RECONSTRUCTION AND REPAIRS SHALL INCLUDE DAMAGE TO THE FINISH OR FURNISHING OF THE BUILDING RESULTING FROM THE ORIGINAL DEFECT OR REPAIR THERETO. 41. PROVIDE HEAD GUARDS ON ALL SPRINKLERS IN MECHANICAL ROOMS, ELECTRICAL ROOMS, ELEVATOR PITS & MACHINE ROOMS AND ALL ROOMS WITH EXPOSED CEILINGS. 42. SPRINKLER HEADS SHALL BE A MINIMUM OF 12' FROM ANY DIFFUSER PER NFPA 13. 43. INSTALL SPRINKLERS AT BASE OF ELEVATOR HOIST WAYS NO HIGHER THAN 22' ABOVE THE FLOOR OF THE PIT. 44. PROVIDE SPRINKLERS ABOVE AND BELOW DUCTWORK, CONDUIT. PIPING, ETC. 48' IN WIDTH AND LARGER. THIS INCLUDES SYSTEMS LOCATED ADJACENT TO EACH OTHER WHICH THEIR COMBINED WIDTH IS 48' OR LARGER. 45. PIPING SHALL NOT BE RUN OVER ANY ELECTRICAL AND PHONE PANELS OR EQUIPMENT. 46. THE FIRE PROTECTION CONTRACTOR SHALL KEEP A SET OF MARKED UP DRAWINGS AS THE JOB PROGRESSES. NO MAJOR CHANGE SHALL BE MADE TO FIRE PROTECTION DESIGN ENGINEERING UNLESS IT HAS BEEN COORDINATED, DRAWN AND SUBMITTED FOR APPROVAL. 47. FIRE PROTECTION SERVICES TO BE REMOVED SHALL BE CAPPED. 48. CONTINUITY OF SERVICE: INTERRUPTIONS OF EXISTING SERVICES OR FACILITIES SHALL BE KEPT TO A MINIMUM AND THE CONTRACTOR SHALL FURNISH ALL MATERIALS AND LABOR REQUIRED WHENEVER TEMPORARY CONNECTIONS ARE NECESSARY TO MAINTAIN CONTINUITY OF SERVICE. INTERRUPTIONS OF THE EXISTING SERVICES, THE INSTALLATION OF TEMPORARY FACILITIES, AND THE WORK OF MAKING FINAL CONNECTIONS TO NEW WORK SHALL BE DONE ONLY AT SUCH TIMES AS PERMITTED AND SCHEDULED BY THE OWNER. ALL SUCH CONNECTIONS AND TIE-INS SHALL BE COORDINATED THROUGH THE OWNERS PROJECT MANAGER. I. THE DURATION OF EACH SHUTDOWN SHALL BE LIMITED TO NIGHTS AND /OR WEEKENDS WITH THE TIME FRAME FOR SHUTDOWNS AS SPECIFIED BY THE OWNER. THE CONTRACTOR SHALL NOTIFY THE OWNER IN WRITING FORTY -EIGHT (48) HOURS IN ADVANCE OF EACH REQUIRED INTERRUPTION OF EXISTING SERVICE. ANY AREA AFFECTED BY SHUTDOWN SHALL REQUIRE A 24 HOUR /7 DAYS PER WEEK FIRE WATCH. 2. THE CONTRACTOR SHALL INCLUDE IN BID PRICE ALL PREMIUM TIME CHARGES FOR LABOR AND EQUIPMENT REQUIRED FOR ALL NIGHT AND WEEKEND OVERTIME WORK, AS NECESSARY, TO COMPLETE THE SCOPE OF THE CONTRACT. 49. SSR IS CONTRACTED BY THE HOSPITAL /OWNER TO BE THE ENGINEER OF RECORD FOR THIS PROJECT. CONTRACTOR SHALL PRODUCE SHOP DRAWINGS WHICH MATCH THESE DRAWINGS IN DESIGN INTENT (PIPE ROUTING. PIPE SIZING, SPRINKLER HEAD LAYOUT. ETC.). CONTRACTOR SHALL COORDINATE FIRE PROTECTION INSTALLATION WITH SITE CONDITIONS (STRUCTURE, CEILING, DUCTWORK, PIPING, CONDUIT, ETC.), AND PROVIDE OFFSETS TO PIPE ROUTING OR DEVIATIONS FROM DESIGN INTENT ONLY WHERE REQUIRED BY SITE CONDITIONS OR APPLICABLE CODES. 50. CONTRACTOR SHALL COORDINATE WITH FIRE ALARM CONTRACTOR FOR THE ADDITION OR REMOVAL OF FIRE ALARM DEVICES INCLUDING FLOW AND TAMPER SWITCHES. FLOW AND TAMPER SWITCHES SHALL TIE INTO THE HOSPITAL'S MAIN FIRE ALARM PANEL TO MAINTAIN SHUTDOWN OF EXISTING AIR HANDLING UNITS AND EXHAUST FANS DURING FIRE ALARM CONDITIONS. 51. CONTRACTOR SHALL PATCH WALLS, FLOORS, ROOFING AND CEILINGS TO MATCH EXISITNG FINISHES FOR DEMOLITION AND INSTALLATION OF FIRE PROTECTION SYSTEMS. COORDINATE WITH ARCHITECTURAL DRAWINGS. 52. ALL EXTERIOR HANGERS SHALL BE GAAVANIZED STEEL. 53. CONTRACTOR SHALL PROVIDE ALLOWANCE IN BID FOR AN ADDITIONAL 20 CONCEALED HEADS WITH 10 FOOT 11 ARMOVER, 1 TEE AND 2 ELBOWS TO EACH HEAD. PROVIDE LINE ITEM COST PER HEAD WITH ASSOCIATED ARMOVER, FITTINGS AND HANGERS. 54. ALL EQUIPMENT AND PIPES IN MECHANICAL ROOMS SHALL BE LABELED. PIPE LABELS SHALL INCLUDE DIRECTION OF FLOW. 55. PIPES FOR FUTURE USE SHALL BE CAPPED ABOVE CEILING. 56. PROVIDE A MINIMUM OF 6 INCHES IN BETWEEN ALL PIPING AND FIRE RATED AND SMOKE TIGHT PARTITIONS FOR REQUIRED INSPECTIONS. ANY PIPING WITHIN THIS 6 INCHES SPACE SHALL BE REQUIRED TO BE MOVED AND REROUTED. ANY COST IMPACT TO OTHER TRADES WILL BE THE RESPONSIBILITY OF THE CONTRACTOR. 57. ENGINEERING SERVICES TO BE REMOVED SHALL BE CAPPED AND PLUGGED. 58. REFER TO DIVISION 15 SPECIFICATIONS FOR MORE INFORMATION. 59. CONTRACTOR SHALL PROVIDE 24/7 FIRE WATCH FOR ALL AREAS OF THE HOSPITAL THAT HAVE THE FIRE PROTECTION SYSTEM SHUTDOWN FOR 4 HOURS OR MORE AS REQUIRED PER THE FLORIDA FIRE PREVENTION CODE 2007. COORDINATE REQUIREMENTS WITH OWNER. 60. CONTRACTOR SHALL OBTAIN FROM THE OWNER A COPY OF THE INFECTION CONTROL RISK ASSESSMENT (ICRA) PREPARED FOR THIS PROJECT. CONTRACTOR SHALL REVIEW THE REQUIREMENTS IN THE REPORT AND PERFORM ALL WORK IN ACCORDANCE WITH THOSE REQUIREMENTS. SEE MECHANICAL DRAWINGS FOR COORDINATION OF VENTILATION REQUIREMENTS REQUIRED BY ICRA. FIRE PROTECTION LEGEND SYMBOL DESCRIPTION SYMBOL DESCRIPTION F FIRE LINE OR MAIN F.E. FIRE DEPARTMENT VALVE CABINET -A/S- AUTOMATIC SPRINKLER MAIN FP -1, ETC FIXTURE INDENTIFICATION D DRAIN LINE F.SP. CONNECTION TO EXISTING O.S. & Y. PIPE TURNED UP • FIRE EXTINGUISHER A.F.F. PIPE TURNED DOWN T.S. FLOW SWITCH 6 BALL VALVE- F.D.V. CAP ON LINE -11 CHECK VALVE PASSENGER ELEVATOR AT CHILDRENS CENTER 1ST FLOOR AND - Ill UNION IN PIPE PIPING TO BE REMOVED FIRE PROTECTION DETAILS O.S. &Y. GATE OR BUTTERFLY VALVE W /TAMPER SWITCH. REMOVE EXISTING HEAD AND PLUG FITTING ---{�� --W CHECK VALVE REMOVE EXISTING HEAD & EXTEND V BRANCH LINE TO NEW HEAD LOCATION CONTROL VALVE AND CHECK VALVE WITH FLOW AND TAMPER SWITCHES FIRE COMPONENT SCHEDULE IDENTITY COMPONENT FP -1 FIRE EXTINGUISHER (BC - 10 LB. - WALL HUNG) F.E. FIRE EXTINGUISHER F.E.0 FIRE EXTINGUISHER CABINET FIRE PROTECTION ABBREVIATIONS F.H.C. FIRE HOSE CABINET E.P. ELECTRICAL PANEL F.E. FIRE EXTINGUISHER F.E.0 FIRE EXTINGUISHER CABINET A/S AUTOMATIC SPRINKLER F.M.C. FIRE DEPARTMENT VALVE CABINET F.SP. FIRE STANDPIPE O.S. & Y. OUTSIDE STEM AND YOKE RCV RISER CONTROL VALVE A.F.F. ABOVE FINISHED FLOOR T.S. TAMPER SWITCH F.S. FLOW SWITCH F.D.V. FIRE DEPARTMENT VALVE FP2.4 PASSENGER ELEVATOR AT CHILDRENS CENTER 1ST FLOOR AND 2ND FLOOR - NEW WORK - FIRE PROTECTION SPRINKLER HEAD LEGEND TYPE K -FACT TEMP LOCATION 1. SIDE WALL - ORS 5.6 225° BASE OF ELEVATOR SHAFTS 2. UPRIGHT - ORS 5.6 225° TOP OF ELEVATOR SHAFTS 3. UPRIGHT - ORS 5.6 2250 ELEVATOR MACHINE ROOMS. WHITE POLYESTER FP2.2 PASSENGER ELEVATORS #9 & 10 1ST FLOOR, 7TH FLOOR AND ELEVATOR MACHINE ROOM - NEW WORK - FIRE * SEE SPECIFICATIONS FOR MODEL NUMBERS. * PLUG ALL UNUSED OUTLETS. 1 r � .. I REVISIONS- D 0 A �tn QOD rn z� 0 -__I Qo ran LL;l X Q W 0 V7 z0 Ld I V) Q M qw OD O W W QI w N� �-- O Cr N to W O�a M W (� 'o w C 0 x F° 0 U) QU �W 9 r O Qie� SRSmith Seckman Reid, Inc. 600 West Hillsboro, Suite 300 Deerfield Beach, FL 33441 (954) 421 -1260 FAX: (954) 421 -1466 www.ssr- inc.com Firm Certification - EB- 0000857 John E. Moulder PE -83200 Michael A. St-ard PE . 56701 Dennis Davie PE - 58588 SSR JOB # 1032045.0 x v) L_ J W J z C� L. J (_D =z V) d z � CD 0 P- C1 U z L1J Q C7 ('r, 0 � Z W w � U _ L1J DRAWN: CHECKED: IDATE: 06 -30-10 1 \�' �,• M V � raj d" N J Shee No. FPO.] OF JOB R 2003 1 ra DRAWING INDEX SHEET NUMBER SHEET TITLE FP0.1 FIRE PROTECTION SCHEDULES, LEGENDS AND DRAWING INDEX FP2.1 SERVICE ELEVATOR #8 1ST FLOOR, 7TH FLOOR AND ELEVATOR MACHINE ROOM - NEW WORK - FIRE PROTECTION FP2.2 PASSENGER ELEVATORS #9 & 10 1ST FLOOR, 7TH FLOOR AND ELEVATOR MACHINE ROOM - NEW WORK - FIRE PROTECTION FP2.3 RECIEVING ELEVATOR #11 IST FLOOR AND 2ND FLOOR - NEW WORK - FIRE PROTECTION FP2.4 PASSENGER ELEVATOR AT CHILDRENS CENTER 1ST FLOOR AND 2ND FLOOR - NEW WORK - FIRE PROTECTION FP5.1 FIRE PROTECTION DETAILS 1 r � .. I REVISIONS- D 0 A �tn QOD rn z� 0 -__I Qo ran LL;l X Q W 0 V7 z0 Ld I V) Q M qw OD O W W QI w N� �-- O Cr N to W O�a M W (� 'o w C 0 x F° 0 U) QU �W 9 r O Qie� SRSmith Seckman Reid, Inc. 600 West Hillsboro, Suite 300 Deerfield Beach, FL 33441 (954) 421 -1260 FAX: (954) 421 -1466 www.ssr- inc.com Firm Certification - EB- 0000857 John E. Moulder PE -83200 Michael A. St-ard PE . 56701 Dennis Davie PE - 58588 SSR JOB # 1032045.0 x v) L_ J W J z C� L. J (_D =z V) d z � CD 0 P- C1 U z L1J Q C7 ('r, 0 � Z W w � U _ L1J DRAWN: CHECKED: IDATE: 06 -30-10 1 \�' �,• M V � raj d" N J Shee No. FPO.] OF JOB R 2003 1 ra