09-1110-024W
J
W
w
a
PLUMBING NEW CONSTRUCTION NOTES
1. PLUMBING INSTALLATION OF ALL FIXTURES, EQUIPMENT, AND PIPING
SHOWN ON THESE DRAWINGS SHALL BE INSTALLED IN ACCORDANCE
WITH ALL APPLICABLE STATE, LOCAL AND HEALTH CODES
REQUIREMENTS.
2. CONTRACTOR SHALL FIELD VERIFY ELEVATIONS, SIZES AND
LOCATIONS OF EXISTING PLUMBING AND MEDICAL GAS PRIOR TO BIDDING. IF
DISCREPENCIES ARE FOUND, THEY ARE TO NOTIFY ENGINEER.
3. ALL PLUMBING FIXTURES TO COMPLY WITH TABLE 604.3 OF THE FLORIDA
BUILDING CODE - 2007
4. CONTRACTOR SHALL COORDINATE EQUIPMENT CONNECTIONS & MOUNTING
HEIGHTS WITH EQUIPMENT AND ARCHITECTURAL DRAWINGS
AND SUPPLIER. INSTALL EQUIPMENT AND MAKE FINAL
CONNECTIONS FURNISHING CUTOFF VALVES, P- TRAPS, FITTINGS,
P.R.V.'S, AND PIPING AS REQUIRED. CONTRACTOR SHALL OBTAIN
A SET OF THE EQUIPMENT DRAWINGS PRIOR TO BIDDING IN ORDER
TO DETERMINE ALL REQUIRED CONNECTIONS.
5. CALLEDTFOR AS BEING RE USED ORPFURNISHEDHBY OTHENEW, EXCEPT THAT
6. CONTRACTOR SHALL PROVIDE ROUGH -INS AND MAKE FINAL CONNECTIONS
FOR EACH PIECE OF EQUIPMENT REQUIRING PLUMBING CONNECTION,
INCLUDING TAILPIECES, TRAPS, LINE STRAINERS, STOP VALVES, GAUGES,
VACUUM BREAKERS, REDUCING VALVES, SPECIAL FITTINGS,
INSULATION, AND ALL NECESSARY DEVICESFOR A COMPLETE
AND OPERATIVE SYSTEM. COORDINATE EXACT REQUIRED
PLUMBING ROUGH -INS WITH VENDOR SUPPLIER DRAWINGS.
7. THE CONTRACTOR SHALL INSTALL PLUMBING PIPING IN LOCATIONS INDICATED
ON THE CONTRACT DOCUMENTS. THE ONLY DEVIATION FROM THIS WOULD BE
IF ADDITIONAL OFFSETS ARE REQUIRED TO COORDINATE WITH OTHER TRADES.
IF THE THE CONTRACTOR DESIRES TO CHANGE THE PLUMBING ROUTING FOR
ANY OTHER REASON, HE SHALL COMPENSATE THE ENGINEER AT A RATE OF
DPE x 2.75 TO REVISE THE PLUMBING DRAWINGS, RISER DIAGRAMS AND FOR
THE TIME INVOLVED IN REISSUING DRAWINGS TO THE AUTHORITY HAVING
JURISDICTION. CONTRACTOR SHALL CONTACT ENGINEER FOR ESTIMATED TIME
REQUIRED AND SCHEDULE FOR PERFORMING WORK.
8. REPAIR /REPLACE EXISTING VALVES WHICH DO NOT HOLD WHEREVER NEW
PIPING IS CONNECTED TO EXISTING PIPING, AND THE EXISTING VALVES ARE
TO BE REUSED.
9. SEAL PENETRATIONS OF FIRE RATED WALLS AND FLOORS IN ACCORDANCE
WITH U.L. FIRE RESISTANCE INDEX FOR THROUGH PENETRATION FIRE STOP
SYSTEMS. COORDINATE REQUIREMENTS WITH ARCHITECTURAL PLANS AND
SPECIFICATIONS.
10. CONTRACTOR SHALL FURNISH AND INSTALL SHOCK ABSORBERS ON ALL LINES
SERVING QUICK CLOSING VALVES AND AS INDICATED ON PLUMBING PLANS AND
RECOMMENDED BY THE MANUFACTURER.
11. CONTRACTOR SHALL COORDINATE WITH ALL DISCIPLINES INVOLVED SO AS TO
AVOID ANY PIPE ROUTING PROBLEMS.
12. PROVIDE OFFSETS AND FITTINGS AS REQUIRED.
13. CHANGES IN THE DIRECTION OF SANITARY PIPING SHALL NOT BE MADE WITH
FITTINGS WHICH WILL CAUSE EXCESSIVE REDUCTION IN THE VELOCITY OF FLOW
OR CREATE ANY OTHER ADVERSE EFFECT UNLESS PHYSICALLY IMPOSSIBLE
OE: USE OF SANITARY TEE IN A HORIZONTAL CONNECTION, USE OF A DOUBLE
SANITARY TEE IN A VERTICAL STACK, IN GENERAL, USE OF SHORT- RADIUS
FITTING FOR BRANCH TO HOUSE DRAIN OR STACK CONNECTION).
14. THIS CONTRACTOR SHALL BASE HIS PROPOSAL UPON THE EQUIPMENT AS
SCHEDULED OR SPECIFIED, USING THE MANUFACTURERS AND MODEL NUMBERS
AS CALLED FOR IN THE SPECIFICATIONS AND SCHEDULED ON
THE DRAWINGS. IF MORE THAN ONE MANUFACTURER OF EQUIPMENT IS
SPECIFIED, ANY ONE OF THE MANUFACTURERS OF EQUIPMENT MAY BE USED IN
THIS CONTRACTOR'S PROPOSAL. IF THIS CONTRACTOR
WISHES TO USE EQUIPMENT NOT SPECIFIED HE MUST, AT THE TIME OF BIDDING,
SUBMIT SEPARATELY ON LETTERHEAD STATIONARY OF THE BIDDER, THE
EQUIPMENT HE WOULD SUBSTITUTE AND THE COST TO BE ADDED OR TO BE
DEDUCTED FROM HIS PROPOSAL.
15. THE CONTRACTOR IS EXPECTED TO ORDER ALL MATERIALS IN SUFFICIENT TIME
TO AVOID DELAYING THE COMPLETION OF THE PROJECT. DELAY IN DELIVERIES
WILL NOT BE CONSIDERED A JUSTIFIABLE REASON FOR SUBMISSION OF
SUBSTITUTE MATERIALS.
16. CONTRACTOR IS RESPONSIBLE FOR RELOCATING ALL EXISTING SANITARY,
STORM, CONDENSATE, MEDICAL GAS AND WATER PIPING TO FACILITATE THE
INSTALLATION OF NEW ELECTRICAL & MECHANICAL SYSTEMS. THIS INCLUDES
ALL CEILING SPACES, SHAFTS, WALLS, ETC.
17. CONTRACTOR SHALL COORDINATE WITH ALL DISCIPLINES INVOLVED AND
EXISTING CONDITIONS ABOVE CEILINGS SO AS TO AVOID ANY PIPE ROUTING
PROBLEMS.
18. WARRANTY /GUARANTEE
A. THE CONTRACTOR SHALL WARRANTY /GUARANTEE AND MAINTAIN THE STABILITY
OF WORK AND MATERIALS AND KEEP SAME IN PERFECT REPAIR AND CONDITION
FOR THE PERIOD OF ONE YEAR.
B. DEFECTS OF ANY KIND DUE TO FAULTY WORK OR MATERIALS, APPEARING
DURING THE ABOVE MENTIONED PERIOD, MUST BE IMMEDIATELY REPAIRED BY
THE CONTRACTOR AT HIS OWN EXPENSE TO THE ENTIRE SATISFACTION OF THE
OWNER AND ENGINEER. SUCH RECONSTRUCTION AND REPAIRS SHALL INCLUDE
DAMAGE TO THE FINISH OR FURNISHING OF THE BUILDING RESULTING FROM THE
ORIGINAL DEFECT OR REPAIR THERETO.
19. PIPING SHALL NOT BE RUN OVER ANY ELECTRICAL AND PHONE PANELS. REROUTE
PIPING AS REQUIRED.
20. CONTRACTOR SHALL PROVIDE ALL LOW VOLTAGE WIRING AND CONDUIT FOR
SENSOR OPERATED FIXTURES. COORDINATE WITH DIVISION 16.
21. THE PLUMBING CONTRACTOR SHALL KEEP A SET OF MARKED UP DRAWINGS
AS THE JOB PROGRESSES. NO MAJOR CHANGE SHALL BE MADE TO PLUMBING
DESIGN ENGINEERING UNLESS IT HAS BEEN COORDINATED, DRAWN AND SUBMITTED
FOR APPROVAL.
22. ENGINEERING SERVICES TO BE REMOVED ! SHALL BE CAPPED AND PLUGGED.
23. CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGES TO EXISTING PIPING
AND FIXTURES DUE TO NEW CONSTRUCTION AND SHALL RESTORE EXISTING
WORK DISTURBED TO IT'S ORIGINAL CONDITION AT NO COST TO THE OWNER.
24. CONTINUITY OF SERVICE: INTERRUPTIONS OF EXISTING SERVICES
OR FACILITIES SHALL BE KEPT TO A MINIMUM AND THE
CONTRACTOR SHALL FURNISH ALL MATERIALS AND LABOR
REQUIRED WHENEVER TEMPORARY CONNECTIONS ARE NECESSARY
TO MAINTAIN CONTINUITY OF SERVICE. INTERRUPTIONS OF THE
EXISTING SERVICES, THE INSTALLATION OF TEMPORARY FACILITIES,
AND THE WORK OF MAKING FINAL CONNECTIONS TO NEW WORK
SHALL BE DONE ONLY AT SUCH TIMES AS PERMITTED AND SCHEDULED
BY THE OWNER. ALL SUCH CONNECTIONS' AND TIE -INS SHALL BE
COORDINATED THROUGH THE OWNERS PROJECT MANAGER.
I. THE DURATION OF EACH SHUTDOWN SHALL BE LIMITED TO NIGHTS AND /OR
WEEKENDS WITH THE TIME FRAME FOR SHUTDOWNS AS SPECIFIED BY THE
OWNER. THE CONTRACTOR SHALL NOTIFY THE OWNER IN WRITING FORTY -EIGHT
(48) HOURS IN ADVANCE OF EACH REQUIRED INTERRUPTION
OF EXISTING SERVICE. j
2. THE CONTRACTOR SHALL INCLUDE IN BID PRICE ALL PREMIUM TIME
CHARGES FOR LABOR AND EQUIPMENT REQUIRED FOR ALL NIGHT AND
WEEKEND OVERTIME WORK, AS NECESSARY, TO COMPLETE THE SCOPE
OF THE CONTRACT.
25. PIPING ROUTED PARALLEL TO A WALL, RATED OR CORRIDOR SHALL BE INSTALLED
WITH MINIMUM 6' CLEARANCE TO ALLOW FOR INSPECTION OF WALL PENETRATIONS.
CONTRACTOR SHALL PROVIDE 12' CLEARANCE WHERE POSSIBLE. COORDINATE
WITH OTHER TRADES AND EXISTING CONDITIONS.
26. CONTRACTOR SHALL PROVIDE (2) COMPLETE SETS OF AS BUILT DRAWINGS ALONG
WITH ALL CLOSE OUT DOCUMENTS PRIOR TO PROJECT COMPLETION.
PLUMBING ABBREVIATIONS
C.W
COLD WATER
OFCI
OWNER FURNISHED CONTRACTOR INSTALLED
H.W.
HOT WATER
R.D.
ROOF DRAIN
H.W.R.
HOT WATER RECIRC
F.D.
FLOOR DRAIN
Y.T.R.
VENT THRU ROOF
P.R.V.
PRESSURE REDUCING VALVE
A.V.T.R.
ACID VENT THRU ROOF
R.P.B.P.
REDUCED PRESSURE BACKFLOW PREVENTER
W.
WASTE (INTERIOR)
A.F.F.
ABOVE FINISHED FLOOR
R.W.L.
RAIN WATER LEADER
A.F.G.
ABOVE FINISHED GRADE
S.W.
STORM WATER
A.W.
ACID WASTE
I.E.
INVERT ELEVATION
A.P.
ACCESS PANEL
C.O.
CLEANOUT
W.C.O.
WALL CLEANOUT
C.D.
CONDENSATE
S.S.
SANITARY SEWER
C.F.C.I.
CONTRACTOR FURNISHED CONTRACTOR INSTALLED
V.I.V.
VALVE IN VERTICAL
A.H.0
AIR HANDLING UNIT
F.C.0
FAN COIL UNIT
PLUMBING LEGEND
SYMBOL DESCRIPTION
SYMBOL DESCRIPTION
-
COLD WATER
i
BALL VALVE
- --
HOT WATER
%r
CHECK VALVE
- - - --
HOT WATER RECIRCULATION
-F}t-
UNION IN PIPE
- -W-
WASTE LINE
----
SECTIONAL CONTROL VALVE
- -V --
VENT PIPE (ABOVE OR BELOW GROUND)
EXTERIOR CLEANOUT
-RWL-
RAIN WATER LEADER
P -I,ETC
FIXTURE INDENTIFICATION
-��
CLEANOUT (ABOVE CEILING)
CONNECTION TO EXISTING
,x
BALANCING VALVE CIRCUIT SETTER
WITH CHECK VALVE
CAP ON LINE
--o
PIPE TURNED UP
PIPE TURNED DOWN
PLUMBING DEMOLITION NOTES
I. EXISTING SERVICES INDICATED ON THESE DRAWINGS = "" WERE DERIVED FROM EXISTING DRAWINGS AND "
LIMITED FIELD OBSERVATIONS. THESE DRAWINGS - =-
MAY NOT BE ALL INCLUSIVE OF SERVICES THAT
EXIST IN THE PROJECT AREA. CONTRACTOR SHALL
VERIFY SERVICES, LOCATION, TYPE, AND SIZE
PRIOR TO ANY CONSTRUCTION. ANY DEVIATIONS
IMPACTING WORK SHOWN ON THESE DOCUMENTS SHALL
BE REPORTED TO THE ARCHITECT FOR COORDINATION
PRIOR TO CONSTRUCTION.
2. EXISTING SERVICES, EQUIPMENT, AND FIXTURES, TO
REMAIN OR TO BE RELOCATED, SHALL BE REPAIRED
TO ORIGINAL OPERATION OR REPLACED, SHOULD THEY
BE DAMAGED DURING CONSTRUCTION.
3. ALL EXISTING WORK NOT SHOWN ON THESE DRAWINGS
(UNLESS NOTED OTHERWISE) SHALL REMAIN AS IS.
4. ALL PENETRATIONS OR OPENINGS FROM REMOVED
PIPES THROUGH EXISTING BUILDING
WALLS AND FLOORS SHALL BE SLEEVED AND /OR
PATCHED TO MATCH ORIGINAL. SEE ARCHITECTURAL
DRAWINGS FOR FINAL FINISHES.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE
TO EXISTING PIPING , FIXTURES, MED GAS OUTLETS OR EQUIPMENT
DUE TO NEW CONSTRUCTION AND SHALL RESTORE EXISTING
WORK TO ITS ORIGINAL CONDITION AT NO COST TO THE
OWNER.
6. CONTINUITY OF SERVICES: EXISTING BUILDING WILL REMAIN IN
USE DURING CONSTRUCTION OPERATIONS. WHEN AN INTERRUPTION
OF AN EXISTING SERVICE IS NECESSARY, CONTRACTOR SHALL
COORDINATE WITH AUTHORIZED HOSPITAL PERSONNEL BEFORE
MAKING THE NECESSARY INTERRUPTION.
7. CONTRACTOR TO REMOVE EXISTING STACKS AND RISERS LOCATED IN
EXISTING WALLS TO BE DEMOLISHED AND PROVIDE NEW OFF -SET AT
CEILING ABOVE AND BELOW AND DROP THROUGH FLOOR AND RECONNECT
TO EXISTING SERVICES AT THE FLOOR BELOW AND CEILING ABOVE.
8. CONTRACTOR TO FIELD VERIFY THAT ALL EXISTING PLUMBING AND MEDICAL GAS
-
TO BE REMOVED DOES NOT AFFECT OTHER AREAS OF THE HOSPITAL THAT
ARE NOT IN CONSTRUCTION AND MUST STAY OPERATIONAL. IF
DISCREPENCIES ARE FOUND THE CONTRACTOR IS TO NOTIFY THE
ENGINEER.
9. CONTRACTOR SHALL REMOVE EXISTING PLUMBING
TO FIXTURES, FIXTURE CARRIERS
AND EQUIPMENT TO BE REMOVED AS SHOWN ON DRAWINGS OR AS REQUIRE{.
CONTRACTOR SHALL CAP SERVICES NEXT TO SERVICE MAINS IN CEILINGS,
WALLS, OR BELOW FLOOR. CONTRACTOR SHALL REROUTE ALL ACTIVE PLUMBING .
SERVICES IN CHASES OR WALLS TO BE REMOVED, TO NEW
CHASE AREAS OR NEW WALLS AS REQUIRED.
10. CONTRACTOR SHALL SUBMIT A COMPLETE LIST OF PLUMBING
FIXTURES AND /OR EQUIPMENT THAT ARE TO BE REMOVED
TO THE LOCAL OWNER'S REPRESENTATIVE. ALL ITEMS THAT THE
LOCAL OWNER'S REPRESENTATIVE WISHES TO RETAIN SHALL BE
TURNED OVER TO THE OWNER AND THE REMAINDER SHALL BE REMOVED
FROM THE SITE AND LEGALLY DISPOSED.
INFECTION CONTROL MEASURES
I. CONTRACTOR SHALL OBTAIN FROM THE OWNER A COPY OF THE INFECTION CONTROL
RISK ASSESSMENT (ICRA) PREPARED FOR THIS PROJECT. CONTRACTOR SHALL REVIEW
THE REQUIREMENTS IN THE REPORT AND PERFORM ALL WORK IN ACCORDANCE WITH
THOSE REQUIREMENTS. CONTRACTOR SHALL STRICTLY ADHERE TO THE LIMITS OF
THE CONSTRUCTION AREA, AND WHERE PHASING APPLIES SHALL ADHERE TO THE
PHASING PLAN. ANY WORK OUTSIDE THE CONSTRUCTION AREA SHALL BE COORDINATED
WITH THE OWNER AND PERFORMED IN ACCORDANCE WITH THE ICRA REPORT, UNDER
THE SUPERVISION OF THE OWNER'S REPRESENTATIVE OR OTHER DESIGNATED ICRA
COMMITTEE OFFICER.
2. TO THE EXTENT THAT IT IS REQUIRED BY THE ICRA, THE CONTRACTOR SHALL
ENDEAVOR TO MAINTAIN EXISTING LEVELS OF INDOOR AIR QUALITY IN AREAS
SURROUNDING AND ADJACENT TO THE CONSTRUCTION WORK ZONE, AND ELSEWHERE
IN THE FACILITY. IT SHOULD BE ANTICIPATED THAT THE ICRA REPORT WILL REQUIRE
MEASURES TO THIS EFFECT INCLUDING ERECTION OF CONSTRUCTION ZONE BARRIERS
AND PROVISION OF NEGATIVE AIR PRESSURE IN THE CONSTRUCTION ZONE RELATIVE
TO OTHER AREAS OF THE FACILITY.
3.IN ADDITION TO THE MEETING THE REQUIREMENTS OF THE ICRA REPORT, THE
CONTRACTOR AT A MINIMUM SHALL PROVIDE EQUIPMENTAND COMPONENTS
NECESSARY TO CREATE A NEGATIVE PRESSURE IN THE CONSTRUCTION WORK ZONE
RELATIVE TO ADJACENT AREA. EXISTING HVAC SYSTEMS AND COMPONENTS SHALL
NOT BE USED FOR THIS FUNCTION, UNLESS SPECIFICALLY APPROVED BY THE OWNER'S
INFECTION CONTROL OFFICER. THE CONCEPT AND ALL ASPECTS OF THIS WORK SHALL
BE DONE IN ACCORDANCE WITH THE ICRA REQUIREMENTS AND AT A MINIMUM AS
FOLLOWS:
VERIFY ALL EXISTING PLUMBING WHICH PASSES THROUGH THE
CONSTRUCTION ZONE, AND IS TO REMAIN, IS SEALED AND PROTECTED
DURING THE CONSTRUCTION DURATION.
AIR REMOVED FROM THE CONSTUCTION ZONE SHALL BE FILTERED AND /OR
DISCHARGED AS DIRECTED BY THE ICRA REPORT.
PRESENT THE NEGATIVE AIR PRESSURE PLAN TO THE OWNER FOR APPROVAL
BY THE INFECTION CONTROL COMMITTEE.
PROVIDE MEANS TO MONITOR AND VERIFY NEGATIVE PRESSURE IS BEING
MAINTAINED IN ACCORDANCE WITH THE ICRA REPORT, AND PROVIDE
DOCUMENTATION TO THE OWNER AS REQUIRED.
4. COORDINATE IN ADVANCE ANY REQUIRED EQUIPMENT SHUTDOWN WITH THE OWNER,
AND VERIFY BEFORE SHUTDOWN THAT EXISTING OR DESIRED AIR PRESSURE
RELATIONSHIPS WILL NOT BE ADVERSALY AFFECTED.
PLUMBING DRA WING INDEX
NO. SHEET TITLE
PO.01
PLUMBING LEGEND, SCHEDULES & DRAWING INDEX
P1.01
ROOF PLAN - DEMOLITION - PLUMBING
P2.01
FIRST FLOOR - NEW WORK - PLUMBING
P2.02
ROOF PLAN - NEW WORK - PLUMBING
P5.01
PLUMBING DETAILS & ISOMETRIC RISERS
mm
I
I®
40
500 `,Nest Hillsboro, Suite 300
- Degrfield Beach, FL 33441
-(954) 421 -1260
FAX: (954) 421 -1466
www.ssr- inc.com
Firm Certification - EB- 0000857
AMrcdEsquhW PE -45M
Erik S. Walter PE - 63929
John E. Moulder PE - 33200
Michael A. Steward PE - 65701
SSR JOB # 0932026.0
z
W
Z W
wv
O
T
J � jM
Q WQ
I- W o
a. Im W O
V) cr M LP
�/ L
OW
..1... Q
C%)
O °o=
co =)
0 0
z C0
F- p
Z) O
Ov
W
s:d''M.•y1ly �.
i
FDRAWN ED
DATE 12/04/09
r,,, ISED
SHEET N0.
PLUMBING LEGEND,
SCHEDULES &
DRAWING INDEX
P0801