12-669-002radioactive materials will be used, all bio hazardous samples and collected, stored and to
be sent to outside labs for analysis or testing.
6. Any discharges to the sanitary sewer system must meet Sewer Discharge limits stipulated
in Section 24 -42(2) of the Miami- Dade County Code.
7. Operations at this facility shall be conducted without any discharges to open ground or to
the storm sewer system.
Improvements: If at any time this facility is found to be performing inadequately,
the owner shall provide the required corrections and /or additional equipment to
operate in compliance with Chapter 24, Miami -Dade County Code.
Approval is hereby granted for: Office based Surgery Center, as described above.
1. Construction is completed according to approved plans.
2. There may be county, municipal, or other local regulations or restrictions to be complied
with by the owner prior to construction of the facilities represented by these plans. We
recommend that appropriate local agencies be consulted before starting construction.
3. No construction shall take place on contaminated soil. If contamination is encountered
during construction, contact the Pollution Remediation Section of the Department of
Environmental Resources Management (DERM).
cc: Leonor Valdes- DERM