8THE CITY OF PLEASANT LIVING
CITY OF SOUTH MIAMI
OFFICE OF THE CITY MANAGER
INTER-OFFICE MEMORANDUM
To: The Honorable Mayor & Members of the City Commission
FROM: Steven Alexander, City Manager
Agenda Item No.: ~ DATE: April 7, 2015
SUBIECT:
A Resolution pursuant to Section 7-16(g) of the Code of Ordinances, extending the
construction hours for the construction project at 6200 SW 73 Street, identified as
Building Permit #15-254.
BACKGROUND:
On March 19, 2015, the city issued a building permit (Permit #15-254) for the re-roofing
of South Miami Hospital's oncology building which is part of the hospital campus located
at 6200 SW 73 Street. Upon review of the current site conditions by the contractor,
Exclusive Construction & Roofing Group, it was found that it would be difficult to perform
the prescribed construction activities due to the nature of the work that is performed
within the building. Because of this unforeseen circumstance, the project would be
delayed into the approaching hurricane season.
ANALYSIS:
According to the attached correspondence from Mr. Rick Avello, president/owner of
Exclusive Construction & Roofing Group, during the weekday hours of 6:30 a.m. to 6:30
p.m., the company cannot work on over three quarters of the roof due to the operation of
the radiation machines that are housed within the building. Because of this, he is
requesting authority from the City Commission to modify the hours of construction.
Currently, the hours of construction are as follows:
• Monday -Friday, from 7:00 a.m. to 6:00 p.m.
• Saturday, from 9:00 a.m. to 5:00 p.m.
• Sunday, ,No construction activity is permitted
At this time, Mr. Avello is requesting the following modification to the hours of
construction that will be used beginning on April 12, 2015 through May 24,2015:
• Sunday, from 9:00 a.m. to 5:00 p.m.
Pursuant to Section 20-7.16(g) of the City Code of Ordinances,
South Miami Hospital Extended Construction Hour Request
April 7, 2015
Page 2 of 2
All construction sites shall comply with the city's noise code. Construction
activity is limited to the hours of 7:00 a.m. through 6:00 p.m. on the
weekdays of Monday through Friday/ and between the hours of 9:00 a.rm
through 5:00 p.m. on Saturday. No construction activity is permitted on
Sunday. Notwithstanding the above, no construction activities shall take
place in, or within 500 feet of, residentially zoned district~ other than those
in the Hometown District on either Saturday or Sunday an~ as to
construction activities in non-residentially zoned districts and in the
Hometown District all days of the week and hours of the day may be
changed by resolution of the City Commission upon a finding of
extraordinary circumstances.
It is important to note that the oncology building where the work is scheduled to take
place is located in the Planned Unit Development-Hospital (PUD-H) zoning district and is
not located within 500 feet of a residential zoning district.
RECOMMENDATION:
Staff recommends that the Mayor and City Commission approve the request for extended
construction hours.
MWL
Z:\Commission Items\201 5\04-07-1 S\South Miami Hospital-Extended Construction Hours Request\SMH Extended Construction
Hour_eM Report.docx
1 RESOLUTION NO. ________ _
2
3 A Resolution pursuant to Section 7-16(g) of the Code of Ordinances, extending the
4 construction hours for the construction project at 6200 SW 73 Street, identified as
5 Building Permit #15-254.
6
7 WHEREAS, pursuant to Section 7-16(g) of the Code of Ordinances, all construction
8 sites shall comply with the city's noise code. Construction activity is limited to the hours of 7:00
9 a.m. through 6:00 p.m. on the weekdays of Monday through Friday; and between the hours of
10 9:00 a.m. through 5:00 p.m. on Saturday. No construction activity is permitted on Sunday.
11 Notwithstanding the above, no construction activities shall take place in, or within 500 feet of,
12 residentially zoned districts, other than those in the Hometown District, on either Saturday or
13 Sunday and, as to construction activities in non-residentially zoned districts and in the
14 Hometown District, all. days of the week and hours of the day may be changed by resolution of
15 the City Commission upon a finding of extraordinary circumstances; and
16
17 WHEREAS, a building permit was issued to Exclusive Construction & Roofing Group,
18 Inc. for the re-roofing of the South Miami Hospital Radiation-Oncology building at 6200 SW 73
19 Street (Building Permit #15-254); and
20
21 WHEREAS, 6200 SW 73 Street is located within the PUD-H zoning district; and
22
23 WHEREAS, the building where the work will be performed is not located within 500
24 feet of or within a residential zoning district; and
25
26 WHEREAS, due to the nature of the work performed in the building, it will be difficult
27 to perform construction activities during the hours of7:00 a.m. to 6:00 p.m.; and
28
29 WHEREAS, Exclusive Construction & Roofing, Inc. is requesting authority to undertake
30 construction activities on Sundays from 9:00 a.m. to 5:00 p.m.; and
31
32 WHEREAS, Exclusive Construction & Roofmg, Inc. is also requesting authority to
33 utilize the revised construction hours beginning April 12, 2015 through May 24, 2015; and
34
35 WHEREAS, approval of this request will not be detrimental or harmful to the
36 surrounding area ofthe community at large; and
37
38 NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY
39 COMMISSION OF THE CITY OF SOUTH MIAMI, FLORIDA:
40
41 Section 1. The request by Exclusive Construction & Roofing, Inc. for an extension to the
42 construction hours for the construction project located at 6200 SW 73 Street, identified as
43 building permit #15-254 is granted. Construction activity is limited to the hours of 7:00 a.m.
44 through 6:00 p.m. on the weekdays of Monday through Friday. Construction activities shall be
45 limited to the hours of 9:00 a.m. to 5:00 p.m. on Saturday and from 9:00 a.m. to 5:00 p.m. on
46 Sunday. The extended construction hours will be effective begiiming April 12, 2015 through
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
May 24, 2015. The owner shall hire, at its own expense, an off duty City of South Miami Police
officer for these days and during the hours from 9:00 a.m. to 5:00 p.m. on Sunday to insure that
the owner and its contractor comply with the City noise ordinance and this resolution. The
construction activity shall be shut down and all work stopped during the extended days and hours
of operation if there is a violation which shall be determined by the City Manager in his sole and
absolute discretion. This resolution may be revoked at any time in the sole and absolute
discretion of the City Commission.
Section 2. Severability. If any section clause, sentence, or phrase of this resolution is for
any reason held invalid or unconstitutional by a court of competent jurisdiction, the holding shall
not affect the validity of the remaining portions of this resolution.
Section 3. Effective Date. This resolution shall become effective immediately upon
adoption by vote of the City Commission.
PASSED AND ADOPTED this __ , day of ___ , 2015.
ATTEST:
CITY CLERK
READ AND APPROVED AS TO FORM,
LANGUAGE, LEGALITY AND
EXECUTION THEREOF
CITY ATTORNEY
APPROVED:
MAYOR
COMMISSION VOTE:
Mayor Stoddard:
Vice Mayor Harris:
Commissioner Liebman:
Commissioner Welsh:
Commissioner Edmond:
To: City Of South Miami
Planning and Zoning Dept.
6130 Sunset Dr.
Ref: Requestto Work on Sundays
To the City Of South Miami we currently have a project in South Miami Hospital at
the Radiation & Oncology Building to re-roof it, we are requesting to work on
Sundays due to the fact that the radiation dept. works from 6:30AM till 6:30PM
Monday through Friday and we cannot work over 3-quarters of the roof due to that
radiation machines. So since we cannot work after 6:00PM Monday through Friday
all we really have is Saturday. The issue with re-roofing is tearing off and installing a
system back to make roof water tight and not cause intrusion and damage very
expensive equipment and maybe even shut down operations, so for us to work over
a section on Saturday and if we cannot finish waiting till next Saturday to continue
we would jeopardize something happening as I mentioned above occurring. By the
way we are not using any noise producing equipment except our trucks for garbage
and torches for the system. This is a very crucial job and we are trying to plan
according so we can get it done before the rainy/hurricane system arrives a couple
of months away. Please let me know if you have any other questions and hopefully
we can get this approved and take care of our client
President/Owner
Exclusive Construction & Roofing Group, Inc
68H SW 81 Terrace
MIIIIIII, Fl :l3143
O. 305-668-2533
F.305-668-25:l4
EXClusive I:onstruction Group
I:GI: # 1519317
Exclusive Roollng & Waterproollng
1:1:1: # 1327918
Lightfoot, Marcus
From:
Sent:
To:
Cc:
Rick Avello <ravello@exclusivecg.com>
Monday, March 30, 2015 11:57 AM
Shari Kamali
Lightfoot, Marcus
Subject: Re: Baptist South Miami Radiation Dept. Re-Roof Sunday Request
Shari great speaking with you today and I apologize again for all the confusion, here is what we are requesting and will
comply with.
We will work from 7am till 5pm Monday through Friday and will also comply with Saturday gam till 5pm
But we are requesting to work:
Sunday gam till5pm, due to the fact that we cannot work over the radiation section that's operates from 6:30am till
6:30pm so we do not have enougth time to finish.
Please if you can help us out with this request would be greatly appreciated,
Sincerely,
Rick Avello
Exclusive Construction & Roofing Group, Inc
305/668-2533
Sent from my iPhone
On Mar 30,2015, at 10:35 AM, Shari Kamali <SKamali@southmiamifl.gov> wrote:
Please call me ASAP.
Shari Kamali
Assistant City Manager
City oj South Miami
6130 Sunset Drive
South Miami, FI33143
DJJice:305-663-6319
Cell: 305-200-4463
SKamali@southmiamif/.qov
<image006.png>
From: Rick Avello [mailto:ravello@exclusivecg.com]
Sent: Monday, March 30, 2015 6:31 AM
To: Lightfoot, Marcus
Cc: Shari Kamali; Citarella, Victor; jsotolongo@exclusivecg.com
Subject: RE: Baptist South Miami Radiation Dept. Re-Roof Sunday Request
Good morning Mr. Lightfoot just wanted to follow up on this request as Baptist is pressuring us to get
this re-roof done before rainy season, just as an fyi we are just re-roofing over the radiation dept and
they work from 6:30Am till 6:30PM Monday through Friday so we are requesting to work from 6:30AM
till 3:00am Monday through Thursday Saturday from 8:00am to 5:00pm and Sunday from 9:00am till
3:00PM to meet our schedule ..
Please let me know as soon as possible,
1
Rick Avello LEED® AP
<image007.png>
6811 S.W. 81st Terrace
Miami, FL 33143
0.305.668.2533
F.305.668.2534
C.786.412.8425
Websltes:
CGC 1519317 -www.ExclusiveCG.com
CCC 1327918 -www.ExclusiveRoofinq.com
RAvello@exciusiveCG.com
<imageOOB.jpg> <image009.jpg>
<image018.gif>
From: Rick Avello [mailto:ravello@exclusivecg.com]
Sent: Thursday, March 26, 2015 10:54 AM
To: 'Citarella, Victor'
Cc: 'Lightfoot, Marcus'; 'Shari Kamali'
Subject: RE: Baptist South Miami Radiation Dept. Re-Roof Sunday Request
Thank you Victor will await Mr. Lightfoot call ..
Sincerely,
Rick Avello LEED® AP
<image007.png>
6811 S.W. 81st Terrace
Miami, FL 33143
0.305.668.2533
F.305.668.2534
c.786.412.8425
Webs/tes:
CGC 1519317 -www.ExciusiveCG.com
CCC 1327918 -www.ExclusiveRoofinq.com
RAvello@exciusiveCG.com
<imageOOB.jpg> <image009.jpg>
<image010.gif>
From: Citarella, Victor [mailto:VCitarella@southmiamifl.gov]
Sent: Thursday, March 26, 2015 10:46 AM
To: Rick Avello
Cc: Lightfoot, Marcus; Shari Kamali
Subject: RE: Baptist South Miami Radiation Dept. Re-Roof Sunday Request
Mr. Avello,
2
Permitted construction days and hours of operation are regulated by our Planning/Zoning
Department. The guidelines are codified under City Ordinance 05-15-2212, copy of which is attached
for your perusal.
Your request has been forwarded to CSM Zoning Review Coordinator Marcus Lightfoot (305-663-6331)
who will contact you directly on this matter.
Tx.
Victor J. Citarella, PE
Director, Building Department
<image011.jpg>
The City of South Miami is a public entity, subjectto Chapter 119 of the Florida Statutes concerning public records. E-mail messages and their
affachrnents are covered under such laws and thus subject to disclosure, All e-mail sent to end received at this address, is captured by our
servers and kept as a public record,
From: Rick Avello [mailto:ravello@exclusivecg.com]
Sent: Tuesday, March 24, 201S 3:49 PM
To: Citarella, Victor; Citarella, Victor
Cc: letimanri@yahoo.com; jsotolongo@exclusivecg.com; yenjg@exclusivecg.com
Subject: Baptist South Miami Radiation Dept. Re-Roof Sunday Request
Good afternoon Gentlemen:
We are a construction and Roofing company and we got awarded a re-roof project at South Miami
Baptist /Radiation-Oncology building, due to the area that we are going to be re-roofing which is over a
radiation building that they do test from 6:30AM till 6:30PM so we are not allowed to work on this roof
and working at night increases areas for accidents to occur as lighting becomes an issue, so have been
told that we need to request permission to work on Sundays because our plans is to work more crews
on Saturday and Sunday to get the job done, we have a City of South Miami re-roof permit attached ..
Please let me know if it's OK or not and or what direction we can,..
Thank you very much for your time,
Sincerely,
Rick Avella LEED® AP
<image007.png>
6811 S.w. 81st Terrace
Miami, FL 33143
0.305.668.2533
F. 305.668.2534
C. 786.412.8425
Webs/tes:
CGC 1519317 -www.Exc/usiveCG.com
CCC 1327918 -www.Exc/usiveRoofinq.com
E-Mail: