CITY OF SOUTH MIAMI
OFFICE OF THE CITY MANAGER
INTER-OFFICE MEMORANDUM
The Honorable Mayor & Members of the City Commission
Steven Alexander, City Manager
Agenda Item NO.:~ September 2, 2014
SUBJECT: A resolution authorizing the City Manager to negotiate and enter into a contract
with the Corradino Group for a total expenditure not to exceed $26,609.48 for
Twin Lakes Traffic Calming Design.
BACKGROUND: A traffic study was performed to assess the magnitude of cut-through traffic in
the neighborhood depicted as Twin Lakes, bounded by SW 62 nd Avenue and
SW 67th Avenue between SW 48 th Street and SW 64th Street, and also the
neighborhood depicted as Bird Estates, between SW 61 st Avenue and 64th
Avenue and between SW 40 th Street and SW 44th Street. For location of
neighborhoods see Exhibit 1 "South Miami Traffic Calming Neighborhood"
map.
Based on the results of the study, traffic calming measures such as speed tables
and a traffic circle are recommended.
In accordance with pursuant to Florida Statute 287.055 for CCNA, The
Corradino Group was one of the firms selected to provide professional
engineering services. The City negotiated hourly rates with the firm and entered
into a professional service agreement with The Corradino Group to perform
engineering services for the City.
Below is a table demonstrating the Traffic & Transportation Firms under the
CCNA.
Firm Project Status
Ty Lin International Mango/ Manor Lane Traffic Calming Design in process
The Corradino Bird Estate & Twin Lakes Traffic Design proposal
Group Calming submitted
Marlin Engineering Pinecrest/ Snapper Creek Traffic Pending design
Calming proposal
C H Perez Cocoplum Traffic Calming Consulting Study phase
URS Crosswalk Pending
TilE CITY OF PLEASANT LIVING
AMOUNT:
ACCOUNT:
CITY OF SOUTH MIAMI
OFFICE OF THE CITY MANAGER
INTER-OFFICE MEMORANDUM
The Corradino Group submitted a proposal in the amount $26,609.48 to perform
the Twin Lakes Traffic Design.
Amount not to exceed $26,609.48
The expenditure shall be charged to the People's Transportation Plan account
number 124-1730-541-6490 which has a balance of $712,942.09, before this
request was made.
ATTACHMENTS: Resolution
Proposal
Exhibit 1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
RESOLUTION NO.: _____ _
A Resolution authorizing the City Manager to negotiate and enter into a contract with the Corradino Group
for a total expenditure not to exceed $26,609.48 for Twin Lakes Traffic Calming Design
WHEREAS, pursuant to Florida Statute 287.055 for CCNA, The Corradino Group was one of the firms selected to
provide professional engineering services; and
WHEREAS, the City negotiated hourly rates with the firm and entered into a professional service agreement with
The Corradino Group to perform engineering services for the City; and
WHEREAS, the Mayor and City Commission wish to provide traffic calming to the area known as Twin Lakes,
bounded by , and
WHEREAS, the total expenditure is not to exceed $26,609.48; and
WHEREAS, the Mayor and City Commission desire to authorize the City Manager to negotiate and enter into a
contract with The Corradino Group for the Twin Lakes Traffic Calming Design for a total amount not to exceed $26,609.48
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COMMISSION OF THE CITY
OF SOUTH MIAMI, FLORIDA THAT:
Section 1: The City Manager is authorized to negotiate the terms and conditions and to execute a contract with
The Corradino Group for the Twin Lakes Traffic Calming Design for an amount not to exceed $26,609.48. A copy of the
proposal is attached.
Section 2: The expenditure shall be charged to the People's Transportation Plan account number 124-1730-541-
6490 which has a balance of$712,942.09, before this request was made.
Section 3: If any section clause, sentence, or phrase of this resolution is for any reason held invalid or
unconstitutional by a court of competent jurisdiction, the holding shall not affect the validity of the remaining portions of this
resolution.
Section 4. This resolution shall take effect immediately upon adoption.
PASSED AND ADOPTED this ___ day of ______ " 2014.
ATTEST:
CITY CLERK
READ AND APPROVED AS TO FORM
LANGUAGE, LEGALITY AND EXECUTION
THEREOF
CITY ATTORNEY
APPROVED:
MAYOR
COMMISSION VOTE:
Mayor Stoddard
Vice Mayor Harris
Commissioner Welsh
Commissioner Liebman
Commissioner Edmond
THE CORRADINO GROUP
Date: August 24, 2014
Dear Mr. Ayala:
CONSULTANT WORK ORDER PROPOSAL
Twin Lakes Neighborhood Traffic Calming
The Corradino Group, Inc. proposes to provide the services identified below for the project entitled
"Twin Lakes Neighborhood Traffic Calming", pursuant to its Professional Service Agreement with
the City of South Miami for Civil Engineering services for Roadway Projects, dated June 28, 2013 .
I. GENERAL
The general objective for the Consultant is to provide all project management and professional
engineering services required for the design and preparation of a complete set of construction
contract plans for a traffic calming devices (Roundabout and Speed Tables), at the following
locations:
• S.W. 63 rd Avenue and S.W. 42 nd Terrace -Roundabout
• S.W. 44th Street from S.W. 64th Avenue to S.W. 62 nd Avenue -1 Speed Hump
• S.W. 63rd Court from S.W. 58th Street to S.W. 62 nd Terrace -2 Speed Humps
• S.W. 65th Avenue from S.W. 64th Street to S.W. 61 st Terrace -1 Speed Humps
Elements of work shall include roadway analysis, topographic survey, signing and pavement
markings, and drainage and geotechnical activities as required. All existing features, i.e. sidewalks,
driveways, etc., requiring repair or replacement, shall also be addressed accordingly.
All plans and design documents are to be prepared with Standard English values in accordance with
all applicable engineering manuals and guidelines.
II. SCOPE OF WORK
Project Activity 4: Roadway Analysis
Task No. 4.4 HorizontalNertical Master Design Files
Includes all efforts required for establishing the master design files for the horizontal and vertical
geometry, existing drainage features, utilities (including conflict location identification and
adjustment), etc. Also includes all work to create elements showing the alignment for the horizontal
geometry in the plan sheets and all efforts required to place labels and required information in the
master design file. In addition, through the use of AUTOTURN, the vehicle path for all roundabouts
will be included as requested, to ensure maneuverability.
Task No. 4.11 Cost Estimate
Includes all work required to prepare a construction cost estimate for each submittal.
Task No. 4.14 Field Reviews
Includes travel time for field visits in order to obtain the necessary data for design.
4055 NW 97th A VENUE • MIAMI, FL 33178
TEL 305.594.0735 • 800.887.5551
FAX 305.594.0755
VlVv'WCORRADINO.COM
August 24, 2014 Page 2
WORK ORDER PROPOSAL
Task No. 4.16 Quality Assurance/Quality Control
Includes implementation of QAlQC plan. Also includes internal peer review and/or constructability
reviews, responses to comments and any resolution meetings if required, and assembly of plans for
submittals for reviews.
Task No. 4.18 Supervision
Includes all effort required to supervise all technical design analysis and plans production.
Task No. 4.19 Coordination
Includes all efforts to coordinate with all disciplines of the project team, including sub-consultants, to
produce a final set of construction documents.
Project Activity 5: Roadway Plans
Task No. 5.1 Key Sheet
Includes efforts for producing the Key Sheet.
Task No. 5.5 Typical Section Sheets
Includes all efforts for development and production of the Typical Section Sheets.
Task No. 5.6 General Notes / Pay Item Notes
Includes all efforts for development and production of the general notes and pay item notes as
required.
Task No.5. 7 Summary of Quantities
CADD production work necessary to complete sheets, does not include the effort required to perform
quantity take offs.
Task No. 5.15 Plan Sheet
Includes production work necessary to develop sheets and all required labeling not included in the
Master Design file.
Task No. 5.21 Miscellaneous Detail Sheet
Includes efforts for developing miscellaneous roadway construction details as required.
Task No. 5.31 Traffic Control Detail Sheets
Includes efforts for developing Traffic Control Detours Sheets
Task No. 5.41 Quality Assurance/Quality Control
Includes implementation of QAlQC plan. Also includes internal peer review and/or constructability
reviews, responses to comments and any resolution meetings if required, and assembly of plans for
submittals for reviews.
Task No. 5.42 Supervision
Includes all efforts required to supervise and coordinate plans production and sUb-consultant
coordination.
Project Activity 6: Drainage
Task No. 6.0 Drainage Analysis/Design
Includes all work required for the design of an isolated storm drain system composed of inlets and/or
manholes with a closed French drain system. Analysis will be based on a 5-year return period using
the rational method and a minimum time of concentration of 10 minutes.
CIPForm116 Revised 7/30/10
August 24,2014 Page 3
WORK ORDER PROPOSAL
Project Activity 7: Utilities
Task No. 7.2 Identify Existing UAOs
Includes identification of all utilities at each intersection by reviewing existing plans, checking with
Sunshine State One Call, City of Miami, and any potential existing SUE reports.
Task No. 7.3 Make Utility Contacts
Includes sending letters and plans to each utility company for coordination.
Task No. 7.10 Review Utility Markups, Work Schedules, Provide Relocation Documents
Includes review of utility marked up plans and work schedules as they are received.
Task No. 7.11 Utility Coordination / Follow-up
Includes coordination and follow-up to ensure the resolution of all known utility conflicts and/or
attainment of utility clearance or "No conflict" letters from each utility company. If there is a conflict
that it can't be resolved, a UWS shall be prepared, coordinated and obtained by the EOR with the
corresponding utility agency.
Project Activity 8: Permitting
Task No. 8.5 Complete and Submit all Required Permit Applications
Includes the following permits and approvals:
Miami-Dade County Public Works Traffic Division approval
DERM/DRER
Project Activity 19: Signing & Pavement Marking Analysis
Task No. 19.3 Reference and Master Design File
Includes all efforts required for establishing the signing and marking master design file to include
reference files of topo, r/w, roadway, etc. Also includes design and layout of signs, lane lines, gores,
pavement markings, rpm's, and all efforts required for drafting.
Task No. 19.7 Quantities
Includes all work required to determine the quantities for each plan sheet.
Task No. 19.9 Cost Estimate
Includes all work required to prepare a construction cost estimate for each submittal.
Task No. 19.14 Quality Assurance/Quality Control
Includes implementation of QAlQC plan. Also includes internal peer review and/or constructability
reviews, verify comments are addressed, assembly of plans for submittals, etc.
Task No. 19.16 Supervision
Includes effort to supervise all technical design analysis.
Project Activity 20: Signing & Pavement Marking Plans
Task No. 20.3 Tabulation of Quantities
Includes time to place pay item numbers, descriptions, quantities and totals on tabulation sheet(s).
Task No. 20.6 Plan Sheet
Includes all efforts required to create the signing and pavement marking sheets.
CIP Form 116 Revised 7/30/10
August 24, 2014 Page 4
WORK ORDER PROPOSAL
Task No. 20.14 Quality Assurance/Quality Control
Includes QC review, verify comments are addressed, resolution meetings and documentation,
assembly of plans for phase submittals, etc.
Task No. 20.15 Supervision
Includes all efforts required to supervise and coordinate plans production and sub-consultant
coordination.
Additional Services
Task No. 3.7 Post Design (Hourly rate as required)
Includes shop drawing reviews, responding to RFI's, plan revisions (not involving errors or
omissions), and limited construction assistance.
Reimbursable Expenses
Project Activity 27: Survey
See attached Scope
Project Activity 30: Geotechnical
See attached Scope
III. SUB-CONSULTANTS
The below listed SUb-Consultants will assist in the performance of the Work.
Sub-Consultant Name Specialty or Expertise
PSI, Inc. Geotechnical Exploration
Longitude Surveyors, LLC Surveying
IV. SCHEDULE OF WORK -TIME OF PERFORMANCE
Consultant shall submit the Deliverables and perform the Work as depicted in the tables below
(Additional pages may be added as needed)
I SCHEDULE OF DELIVERABLES
Task, Sub-task, Duration (specify Delivery Date*
or Activity ID # Major Task, Sub-Task, Activity, or Deliverable weeks or calendar (cumulative weeks, or
days) calendar days)
1 Phase I Submittal -60% Plans 8 weeks ** NTP+ 8 weeks
2 Phase 2 Submittal -90% Plans 4 weeks *** NTP+12weeks
3 Final Submittal -100% Contract Plans 4 weeks *** NTP+16weeks
RE1 Topographic Survey 2 weeks NTP+2 weeks
RE2 Geotechnical Report 2 weeks NTP+2 weeks
* An updated schedule, mdlcatmg actual delivery dates, based on the above duratIOns, Will be proVided to the City upon
receipt of the NTP and will be submitted in Microsoft Project Schedule software.
**Includes time for coordination with Miami-Dade County Public Works Department for concept approval.
***Includes time for review by the City as well as review by the Miami-Dade County Public Works Department. Also
includes time for obtaining all necessary permits.
CIP Form 116 Revised 7/30/10
August 24,2014 Page 5
WORK ORDER PROPOSAL
V. COMPENSATION
Consultant shall perform the Work detailed in this Proposal for a Total fee of twenty-six housand-six
hundred and nine dollars and fouty-eight cents ($26,609.48). The City shall not be liable for any fee,
cost, expense or reimbursable expense or other compensation beyond this amount. Said fee
includes an allowance for Reimbursable Expenses required in connection with the Work, which shall
not exceed $4,955.00. Said Reimbursable Expenses shall be used in accordance with the Agreement
Provisions and shall conform to the limitations of Florida Statutes § 112.061.
SUMMARY OF COMPENSA TlON*
Task, Sub-
task, or
Activity 10 # Major Task Name and/or Activity Description Fee Amount Fee Basis
1 Phase I Submittal (60% Plans) $9,127.06 Lump Sum
2 Phase II Submittal (90% Plans) $4,563.53 Lump Sum
3 Final Submittal (100% Plans) $1,521.18 Lump Sum
AS1 Allowance for Drainage Design (As needed) $2,336.88 Lump sum
AS2 Allowance for Post Design $2,105.84 Lump sum,
Subtotal -Professional Fees $19,654.48 Lump Sum
RE1 Topographic Survey $2,800.00 Lump Sum
RE2 Geotech n ical $2,155.00 Lump Sum
AS3 Allowance for Additional Services $2,000.00 Limiting Amount, not to
(Upon City's PM approval) exceed
TOTAL $26,609.48 . .. .. *Note: Compensation should match the Task, ActIvItIes, and/or Deliverables IdentIfIed .
VI. ADDITIONAL SERVICES
The City may establish an allowance for additional services requested by the City and for unforeseen
circumstances, which shall be utilized at the sole discretion of the City.
VII. DATA PROVIDED BY CITY
The following information or documents are to be provided by the City, if available:
• Right-of-Way Maps
• As-built Information
VIII. PROJECT MANAGER
CONSULTANT'S Project Manager for this Work Order assignment will be Carlos Alcantara, P.E.
Submitted by:
Carlos Alcantara, P.E.
The Corradino Group, Inc.
Reviewed and approval in concept
Recommended by:
Ricardo Ayala, P.E.
City of South Miami Capital Improvements Project Manager
CIPForm116 Revised 7/30/10
Name of Project
County:
FPN:
FAP N "" nU ..
3. Project General Tasks
4. Roadway Analysis
5, Roadway Plans
6. Drainage Analysis
7. Utilities
8. Environmental Permits
Staff Classification
9. Structures -Misc. Tasks, Dwgs, Non-Tech.
10. Structures -BDR
11. Structures -Temporary Bridge
12. Structures -Short Span Concrete
13. Structures -Medium Span Concrete
14. Structures -Structural Steel
15. Structures -Segmental Concrete
16. Structures -Movable Span
17. Structures -Retaining Walls
18. Structures -Miscellaneous
19. Signing & Marking Analysis
20. Signing & Marking Plans
21. Signalization Analysis
22. Signalization Plans
23. Lighting Analysis
24. Lighting Plans
25. Landscape Architecture Analysis
26. Landscape Architecture Plans
27. Survey (Field & Office Support)
28. Photogrammetry
29. Mapping
30. Geotechnical
31. Architecture Development
32. Noise Wall Analvsis
Total Staff Hours
Total Staff Cost
Form Re'IIlSCdJI2BfOS
StaffHourEstimate
Fee Sheet -Prime
ESTIMATE OF WORK EFFORT AND COST -PRIME CONSULTANT
T",n Lake Neighborhood Traffic Calming Project
MiamiMDade
Total Staff Project Sr. Project Project
Hours From Manager Engineer Engineer
"SH
Summarv-$150.00 $162.05 $115.51
28 4 7 8
24 4 6 7
18 2 5 5
14 1 3 3
8 2 0 4
21 2 5 6
22 2 6 7
135 17 32 40
52,550.00 $5,185.60 $4,620.40
Notes:
Engineering
Intern
$108.18
8
9
6
7
3
7
8
48
$5,192.64
1. This sheet to be used by Prime Consultant to calculate the Grand Total fee.
$0.00
Survey Field Days by Subconsultant
4 -Person Crew:
2. Manually enter fee from each subconsultanl. Unused subconsultant rows may be hidden.
Page 12 of 1
SALARY RELATED COSTS:
SUBTOTAL ESTIMATED FEE:
REIMBURSABLE EXPENSES
Subconsultant: Longitude
Subconsultant PSI, Inc.
SUBTOTAL ESTIMATED FEE:
ADDITIONAL SERVICES
Drainage (Limiting Amount, Not to Exceed)
Aditional Services
Consultant Name: The Corradino Group, Inc.
Consultant No.:
Date: 8/19/2014
Estimator: Carlos E. V, -_ .. ,.o>v,.
SH Salary
By Cost By
Activity Activitv
27 $3,524
26 $3,354
18 $2,337
14 $1,740
9 $1,087
20 $2,561
23 $2,946
137
$17,548.64
Check = $17,548.64
Post Design Services (12% of DeSign Fee) (Hourly Rate, Not to Exceed)
GRAND TOTAL ESTIMATED FEE:
Average
Rate Per
Task
$130.51
$129.02
$129.83
$124.28
$120.73
$128.03
$128.10
$128.09
$17,548.64
$17,548.64
52,800.00
$2,155.00
$22,503.64
$2,000.00
$2,105.84
$26,609.48
8/1912014 1:11 PM
Project Activity 4: Roadway Analysis
Estimator: CEV Twin Lake Neighborhood Traffic Calming Project
Task Task Units No of Hours / Total Comments I No. Units Unit Hours
i
4.1 Typical Section Package LS 1 0 0
4.2 Pavement Design Package LS 1 0 0 •
4.3 Access Management LS 1 0 0
4.4 Horizontal Nertical Master Design Files LS 1 15 15 15 hours per Roundabout
4.5 Cross Section Design Files LS 1 0 0
4.6 Traffic Control Analysis LS 1 0 0
4.7 Master TCP Design Files LS 1 0 0
4.8 Design Variations and Exceptions LS 1 0 0
4.9 Design Report LS 1 0 0
4.10 Computation Book & Quantities LS 1 0 0
4.11 Cost Estimate LS 3 2 6 3 hours per each submittal x 2 submittals
4.12 Technical Special Provisions LS 1 0 0
4.13 Other Roadway Analysis LS 1 0 0
Roadway Analysis Technical Subtotal 21
4.14 Field Reviews LS 1 4 4 2 people x 2 hours x 1 review per Roundabout
4.15 Technical Meetings LS 0 0
4.16 Quality Assurance/Quality Control LS % 5% 1
4.17 Independent Peer Review LS % 0% 0
4.18 Supervision LS % 3% 1
Roadway Analysis Nontechnical Subtotal 6
StaffHourEstimate
4. Roadway Analysis Page 2 of 12 8/19/2014
Project Activity 4: Roadway Analysis
Task Task Units No of Hours I Total Comments No. Units Unit Hours
4.19 Coordination LS % 2% 1
4. Roadway Analysis Total 28
StaffHourEstimate
4. Roadway Analysis Page 3 of 12 8/19/2014
Estimator: CEV
Task Task No.
5.1 Key Sheet
5.2 Summary of Pay Items-including Quantity Input
5.3 Drainage Map
5.4 Interchange Drainage Map
5.5 Typical Section Sheets
5.6 General Notes/Pay Item notes
5.7 Summary of Quantities
5.8 Box Culvert Data Sheet
5.9 Bridge Hydraulics Recommendation Sheets
5.10 Summary of Drainage Structures
5.11 Optional Pipe/ Culvert Material
5.12 Project Layout
5.13 Plan/Profile Sheet
5.14 Profile Sheet
5.15 Plan Sheet
5.16 Special Profile
5.17 Back of Sidewalk Profile Sheet
5.18 Interchange Layout Sheet
5.19 Ramp Terminal Details (Plan View)
5.20 Intersection Layout Details
5.21 Miscellaneous Detail Sheets
5.22 Drainage Structure Sheet (per Structure)
StaffHourEstimate
5. Roadway Plans
Scale
Project Activity 5: Roadway Plans
Twin Lake Neighborhood Traffic Calming Project
Units No. of Hours I No. of Total Comments Units Unit Sheets Hours
Sheet 1 3 1 3
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 1 2 1 2
Sheet 1 2 1 2
Sheet 1 2 1 2
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 5 1.4 5 7 3 hours per Roundabout + 1 hour per speed hump
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 0 0 0 0
Sheet 1 2 1 2
EA 0 0 0 0
Page 4 of 12 8/19/2014
Project Activity 5: Roadway Plans
Task Task Scale Units No. of Hours I No. of Total
No. Units Unit Sheets Hours
5.23 Miscellaneous Drainage Detail Sheets Sheet 0 0 0 0
5.24 Lateral Ditch Plan/Profile Sheet 0 0 0 0
5.25 Lateral Ditch Cross Sections EA 0 0 0 0
5.26 RetentionlDetention Ponds Detail Sheet Sheet 0 0 0 0
5.27 Retention Pond Cross Sections EA 0 0 0 0
5.28 Cross-section Pattern Sheet Sheet 0 0 0 0
5.29 Roadway Soil Survey Sheet Sheet 0 0 0 0
5.30 Cross Sections EA 0 0 0 0
5.31 Traffic Control Plan Sheets Sheet 0 0 0 0
5.32 Traffic Control Cross Section Sheets EA 0 0 0 0
5.33 Traffic Control Detail Sheets Sheet 2 2 2 2
5.34 Utility Adjustment Sheets Sheet 0 0 0 0
5.35 Selective Clearing and Grubbing Sheet 0 0 0 0
5.36 Erosion Control Plan Sheet 0 0 0 0
5.37 SWPPP Sheet 2 1 2 2
5.38 Project Control Network Sheet Sheet 0 0 0 0
5.39 Interim Standards LS 0 0 0 0
5.40 Utility Verification Sheet (SUE Data) Sheet 0 0 0 0
Roadway Plans Technical Subtotal 14 22
5.41 Quality Assurance/Quality Control
5.42 Supervision
StaffHourEstimate
5. Roadway Plans
LS
LS
% 5% 1
% 3% 1
5. Roadway Plans Total 14 24
Page 5 of 12
Comments
8/19/2014
Project Activity 6: Drainage Analysis
Estimator: FAL B-30628, Bird Avenue Road Improvements
Task Task Units No of Hours! Total Comments No. Units Unit Hours
6.1 Determine Base Clearance Water Elevation Per Location 0 0 0
6.2 Pond Siting Analysis and Report Per Basin 0 0 0
6.3 Design of Cross Drains EA 0 0 0
6.4 Design of Roadway Ditches Per Ditch Mile 0 0 0
6.5 Design of Outfalls EA 0 0 0
6.6 Design of Stormwater Management Facility EA 0 0 0 : (Offsite Pond)
Design of Stormwater Management Facility
6.7 (Roadside Ditch as Linear Pond or Infield Per System 0 0 0
Pond)
6.8 Design of Flood Plain Compensation Area Per Encroachment 0 0 0
6.9 Design of Storm Drains EA 0 0 0
6.10 Optional Culvert Material LS 0 0 0
6.11 French Drain Systems Per 1000 Feet of 1 8 8 French Drain
6.12 Drainage Wells EA 0 0 0
6.13 Drainage Design Documentation Report LS 1 8 8
6.14 Bridge Hydraulic Report EA 0 0 0
6.15 Temporary Drainage Analysis LS 1 0 0
6.16 Cost Estimate LS 1 0 0
6.17 Technical Special Provisions LS 1 0 0
I
StaffHourEstimate
6. Drainage Analysis-1 6 of 12 8/19/2014
Project Activity 6: Drainage Analysis
Task Task Units No of Hoursl Total Comments No. Units Unit Hours
6.18 Other Drainage Analysis LS 1 0 0
Drainage Analysis Technical Subtotal 16
6.19 Field Reviews LS 1 0 0
6.20 Technical Meetings LS 1 2 2 1 people x 2 hours per meeting
6.21 Quality Assurance/Quality Control LS % 0% 0
6.22 Independent Peer Review LS % 0% 0
6.23 Supervision LS % 0% 0
Drainage Analysis Nontechnical Subtotal 2
6.24 Coordination LS % 0% 0
6. Drainage Analysis Total 18
1
StaffH 0 urEsti mate
6. Drainage Analysis-1 7 of 12 8/19/2014
Estimator: CEV
Task TASK No.
7.1 Kickoff Meeting
7.2 Identify Existing UAOs
7.3 Make Utility Contacts
7.4 Exception Coordination
7.5 Preliminary Utility Meeting
7.6 Individual/Field Meetings
7.7 Collect and Review Plans and Data from UAO(s)
7.8 Subordination of Easements Coordination
7.9 Utility Design Meeting
7.10 Review Utility Markups, Work Schedules,
Processing of Schedules and Agreements
7.11 Utility Coordination / Followup
7.12 Utility Constructability Review
7.13 Additional Utility Services
7.14 Processing Utility Work by Highway Contractor
(UWHC)
7.15 Contract Plans to UAO(s)
7.16 Certification/Close-out
7.17 Other Utilities
StaffHourEstimate
7. Utilities
Project Activity 7: Utilities
Twin Lake Neighborhood Traffic Calming Project
Units No of Hours I Total Hours Comments Units Unit
LS 1 0 0
LS 1 1 1
LS 1 1 1
LS 1 0 0
LS 1 0 0
LS 1 0 0
LS 1 0 0
LS 1 0 0
LS 1 0 0
LS 1 6 6 1 hour x 6 Utilities
LS 1 6 6 6 Utilities x 1 hour per Utility
LS 1 0 0
LS 1 0 0
LS 1 0 0
LS 1 0 0
LS 1 0 0
LS 1 0 0
7. Utilities Total 14
Page 8 of 12 8/19/2014
Staffi-lourEstimate
8. Environmental Permits
Estimator: CEV
Form Revised SIStOS
Task Task No.
8.1 Preliminary Project Research
8.2 Complete Permit Involvement Form
8.3 Establish Wetland Jurisdictional Lines
8.4 Agency Verification of Wetland Data
Project Activity 8: Environmental Permits
Units No. of Hours/ Total
Units Units Hours
LS 1 Q 0
LS 1 l) 0
LS 1 0 0
LS 1 0 0
Tvvin Lake Neighborhood Traffic Calming Project
o
Comments
8.5 Complete And Submit All Required Permit LS 1 8 8 DERM I DRER (4hr) and Miami-Dade Traffic Division Approval
Applications (2hr x 2 submittal)
8.6 Prepare Dredge and Fill Sketches LS 1 0 0
8.7 Prepare USCG Permit Sketches LS 1 0 0
8.8 Prepare Easement Sketches LS 1 0 0
8.9 Prepare RIW Occupancy Sketches LS 1 0 0
8.10 Prepare Coastal Construction Control Line (CCCL) LS 1 0 0 Permit Sketches
8.11 Prepare Tree Permit Information LS 1 0 0
8.12 Mitigation Coordination and Meetings LS 1 0 0
8.13 Mitigation Design LS 1 G 0
8.14 Environmental Clearances LS 1 0 0
8.15 Other Environmental LS 1 Q 0
Environmental Permits Technical Subtotal 8
8.16 Technical Meetings LS 1 0 0
8.17 Quality Assurance/Quality Control LS % O;J,~; 0
8.18 Supervision LS % 0% 0
Environmental Permits Nontechnical SubTotal 0
8.19 Coordination LS % (n~ 0
8. Environmental Permits Total 8
Technical Meetings
WMO EA
ACOE EA
USCG EA 0
USFWS EA 0
FFWCC EA 0 0
FOOT EA (} ()
Other meetings EA 0 0
Subtotal technical meetings
Progress Meetings EA
Phase Review Meetings EA
ITotal Meetings Carries to 8.16
Projectma
Note: Project Manager attendance at progress, phase and field review meetings are manually entered on General Task 3
Page 9 of 12 8/19/2014
Project Activity 19: Signing and Pavement Marking Analysis
Estimator: CEV
Form Revised 6/6/05
Task Task No.
19.1 Traffic Data Analysis
19.2 No Passing Zone Study
19.3 Reference and Master Design File
19.4 Multi Post Sign Support Calculations
19.5 Sign Panel Design Analysis
19.6 Sign Lighting/Electrical Calculations
19.7 Quantities
19.8 Computation Book
19.9 Cost Estimate
19.10 Technical Special Provisions
19.11 Other Signing and Pavement Marking
Units No. of Hoursl
Units Units
LS 1 0
LS 1 0
LS 1 7
EA 0 0
EA 0 0
EA 0 0
LS 3 2
LS 1 0
LS 3 2
LS 1 0
LS 1 0
Signing & Pavement Marking Analysis Technical Subtotal
19.12 Field Reviews LS 1 0
19.13 Technical Meetings LS 1 0
19.14 Quality Assurance/Quality Control LS % 5%
19.15 Independent Peer Review LS % 0%
19.16 Supervision LS % 3%
Signing & Pavement Marking Analysis Nontechnical Subtotal
19.17 I Coordination LS % 2%
StaffHourEstimate
Total
Hours
0
0
7
0
0
0
6
0
6
0
0
19
0
0
1
0
1
2
0
19. Signing & Marking Analysis Page 10 of 12
Twin Lake Neighborhood Traffic Calming Project
Comments
3 hours per Roundabout + 1 hours per speed hump
2 hour x 3 submittals
2 hour x 3 submittals
...
8/19/2014
Project Activity 19: Signing and Pavement Marking Analysis
Task Task Units No. of Hoursl Total Comments •
No. Units Units Hours
•
19. Signing & Pavement Marking Analysis Total 21
StaffHourEstimate
19. Signing & Marking Analysis Page 11 of 12 8/19/2014
Project Activity 20: Signing and Pavement Marking Plans
Estimator: CEV Twin Lake Neighborhood Traffic Calming Project
Task Task Scale Units No of Hours! No. of Total Comments No. Units Unit Sheets Hours
20.1 Key Sheet Sheet 1 0 0
20.2 Summary of Pay Items-including CES Input LS 1 0 0
20.3 Tabulation of Quantities Sheet 5 1 5 1 hour per sheet
20.4 General Notes 1 Pay Item Notes Sheet 0 0 0
20.5 Project Layout Sheet 0 0 0
20.6 Plan Sheet Sheet 5 3 15 3 hours per sheet
20.7 Typical Details EA 0 0 0
20.8 Guide Sign Work Sheet (s) EA 0 0 0
20.9 Traffic Monitoring Site EA 0 0 0
20.10 Cross Sections EA 0 0 0
20.11 Special Service Point Detail EA 0 0 0
20.12 Special Details LS 1 0 0
20.13 Interim Standards LS 1 0 0
Signing & Pavement Marking Plans Technical Subtotal 0 20
20.14 Quality Assurance/Quality Control LS % 5% 1
20.15 Supervision LS % 3% 1
20. Signing & Pavement Marking Plans Total 0 22
--------
StaffHourEstimate
20. Signing & Marking Plans Page 12 of 12 8/19/2014
ITEM #
1
2
3
4
5
1
2
3
4
COST BREAKDOWN
S.W. 63RD AVENUE AND S.W. 42ND TERRACE
CITY OF SOUTH MIAMI, FLORIDA
PSI PROPOSAL NO. 0397-131532
18-Aug-14
DESCRIPTION UNIT
I. Field Exploration
Mobilization of Truck-Mounted Drill Rig Per Job
Percolation Tests Per Test Open Hole Method (Min. 6" Dia.)
Asphalt Cores Each
Closing Holes with Grout/Approved Method(s) to Safeproof Per
Site. [Safeproof to be Accomplished Before Laboratory Lineal
Leaves the Site(s).] Foot
II. Geotechnical Engineering Services
Senior Engineer Per Hour
Project Engineer Per Hour
Senior Engineering Technician Per Hour
CADD/Computer Technician Per Hour
TOTAL PROJECT FEE PER CIRCLE
#OF
UNITS
1.0
1.0
2.0
15.0
1.0
6.0
5.0
2.0
UNIT TOTAL RATE
$ 350.00 $ 350.00
$450.00 $ 450.00
$100.00 $ 200.00
$ 10.00 $ 150.00
$120.00 $ 120.00
$ 90.00 $ 540.00
$ 45.00 $ 225.00
$ 60.00 $ 120.00
$2,155.00
LONGITUDE SURVEYORS, LLC
Monday, August 18, 2014
Carlos E. Verson, P.E. Project Manager
THE CORRADINO GROUP
4055 NW 9ih Avenue, 2nd floor
Miami, FL 33178
VIA EMAIL: cverson@corradino.com
TWIN LAKES.DOCX
In reference to: Surveying services for the intersection of SW 42 Terrace and SW 63 Avenue South Miami, FL
Dear Mr. Verson,
In response to your request regarding a fee estimate for surveying and mapping services for the above referenced
project. LONGITUDE SURVEYORS, LLC (LS) is pleased to submit the following proposal for your consideration.
A. Scope of Services:
LONGITUDE will perform a full Topographic Survey including the following information;
• A Digital Terrain Model (DTM) will be prepared.
• Right-of-Way and property lines for the project area and adjacent properties will be shown graphically.
• A graphical baseline will be created and included.
• Location of all overhead utilities, sidewalks, curb and gutters, paved roads, fences, signs, manholes, catch basins, valves/valve boxes
and any other aboveground improvements within the project area, with elevations.
• Invert and grate elevations for all project area storm and sanitary manholes and catch basins.
• Elevations will be taken at edge of pavement, center of pavement, right-of-way limits and approximately 5 feet beyond wherever
possible. In addition, cross section elevations will be taken at 25-foot intervals.
• LS will collect shots to delineate the driveways beyond the right-of-way whenever possible.
• All elevations will be referenced to the National Geodetic Vertical Datum of 1929 (NGVD29).
• Control points will be set outside the project limits, in locations where they can be used by the contractor during construction.
• All control points will have Northing and Easting coordinates referenced to the Florida State Plane Coordinate System, based on the
North American Datum of 1983/90 and elevations referenced to the National Geodetic Vertical Datum of 1929 (NGVD29).
B. Survey Limits:
City of South Miami intersection of SW 63 Avenue and SW 42 Terrace approximately 250 feet in each direction of the intersection.
C. Deliverables:
LS will deliver signed and sealed originals of the resulting Map of Survey and an electronic copy of the resulting cad file.
D. Schedule:
LS have estimated eight business days to complete this task.
~ Fee:
The total professional fee to complete this task shall be a lump sum of $2,800.00
I understand and agree by signing below "I APPROVE AND ACCEPT" this proposal as a legal binding contract.
By: Date:
(Authorized Signature)
Title:
(Typed or printed name)
I thank you for the opportunity to submit this proposal. We look forward to utilizing our best professional efforts on your behalf on this very
important project.
\/
Eduardo M. Suarez, PSM/PreSidentJ
LONGITUDE SURVEYORS 8290 NW 64th Street· Miami, FL 33166· ph: 305.463.0912· fax: 305.513.5680 ·www.longitudesurveyors.com·
LB7335
South Miami
Traffic Calming
Neighborhoods
Prepared January 2013
Twin Lakes
Study: RFP
Cocoplum
Construction: Complete
Mango Terrace
Study: Complete
Design: RFP
Manof.lane .
Study: Complete
Design: RFP
Pinecrest Villas
Construction: Complete
Study: RFP
CRA
City Road
County Road
III III III State Road
Exhibit 1