06-847-016Plumbing Notes
1. ALL PLUMBING WORK SHALL BE PERFORMED IN ACCORDANCE WITH THE
LATEST EDITION OF THE "FLORIDA BUILDING CODE ", CHAPTER
29, LOCAL ORDINANCE AND IN COMPLIANCE WITH "FLORIDA ENERGY
EFFICIENCY CODE FOR BUILDING CONSTRUCTION.
2. CONTRACTOR TO VERIFY AT SITE LOCATION THE ELEVATION AND SIZE
OF EXISTING WATER AND SEWER MAINS FOR CONNECTION OF NEW
SERVICES BEFORE INSTALLATION OF ANY PIPING.
3. UNDERGROUND METAL PIPING SHALL BE PROTECTED WITH COAT OF
BITUMINOUS COMPOUND ( "BITUSMATIC" OR EQUAL) BEFORE COVERING.
4. PROVIDE SHUT -OFF AND VACUUM BREAKER TO ALL HOSE BIBBS AND
FAUCETS WITH HOSE -END CONNECTION.
5. PLUMBING FIXTURES SHALL BE SUPPLIED BY OWNER AND INSTALLED BY
CONTRACTOR
6. SLOPE OF HORIZONTAL DRAINAGE PIPE:
SIZE (INCHES) MIN. SLOPE (INCH PER FOOT)
2 1/2 OR LESS 1/4
3 TO 6 1/8
8 OR LARGER 1/16
7. PROVIDE FULLY ACCESSIBLE CLEANOUTS ON SANITARY AND ANY WASTE
PIPING AT EVERY CHANGE OF DIRECTION AND AT BOTTOM OF STACKS
CLEAN OUT LOCATION AND SIZES ON HORIZONTAL LINES SHALL BE
ACCORDING TO CODE.
8. VENT LINES SHALL EXTEND 6" MIN. ABOVE ROOF AND FLASHED WITH
LEAD OR CONNECTED TO EXISTING VENT LINES.
9. ALL FLOOR DRAINS SHALL HAVE TRAP PRIMERS TO PROTECT THE SEAL
OF THE TRAP.
10. PROVIDE CONTROL VALVES TO ALL MAINS ENTERING THE BUILDING,
RISERS, BRANCHES, GROUPS OF FIXTURES, AND TO EACH PIECE OF
EQUIPMENT.
11. THE MAXIMUM WATER CONSUMPTION FLOW RATES AND QUANTITIES
FOR ALL PLUMBING FIXTURES FITTINGS SHALL BE IN ACCORDANCE
WITH TABLE 604.4 F.B.C.
3/411.
GOLD WATE1;P,--,
SUPPLY
GATE VA
ELECTRIC WATEIR I- 4EATER
WITI -4 5- "/'EAR WARRANTY,
GLA55 LINED TAN<, DOUG
ELEMENT NON- CONCURREI
ENERGY EFFICIENT INSULA
MEETING ASHRAE 90A -19�
MINIMUM i INSULATION R -fro
4" DEEP DRAIN PAN (WHEN
INSTALLED ABOVE 1st FLR.i
DRAIN V
WATER HAMMER:
A WATER- HAMMER ARRESTOS SHALL
BE INSTALLED WHERE QUICK- CLOSING
VALVES ARE UTILIZED, UNLESS OTHERWISE
APPROVED. WATER- HAMMER ARRESTORS
SHALL CONFORM TO ASSE 1010. ACCESS
SHALL BE PROVIEDED TO WATER- HAMMER
ARRESTORS.
NOTE:
ALL STORM DRAINAGE RUN OFF FROM
ROOF AND TERRACES SHALL TERMINATE
AT GRASSY AREA, AND SHALL BE
RETAINED WITHIN THE PROPERTY.
SEE ARCHITECTURE PLAN.
NOTE:
ALL INDERECT WASTE TO FLOOR DRAINS SHALL BE
2 "MINIMUM WHEN INSTALLED BELOW GRADE.
ALL INDIRECT WASTE PIPING THAT EXCEEDS 2FT IN
LENGTH SHALL BE TRAPPED UNLESS A TRAP IS PROVIDED
INTERNALLY AS PART OF THE APPLIANCE IS IN USE.
IF SUCH APPLIANCE IS IN USE, PROVIDE SPEC SHEET
W /INTERNAL TRAP SHOWN /INTERNAL TRAP SHOWN NOTED
FOR FIELD INSPECTOR'S REVIEW, DURING CONSTRACTION.
ALL FIXTURE DRAINS FROM VENTED LINES SHALL BE PER
FBC 906.1, MAX. OF 10FT. FROM A VENTED 3 "LINE AND
MAXIMUM OF 6FT. FROM A VENTED 2 "LINE.
Piping Materials
1. SANITARY WASTE, VENT AND STORM DRAIN:
POLYVINYL CHLORIDE (PVC) PIPE AND
FITTINGS (SCHEDULE 40). MATERIAL SHALL COMPLY WITH D -1784,
TYPE 1, GRADE 1 COMPOUND. PIPE SHALL COMPLY WITH ASTM D -1785.
FITTIINGS SHALL COMPLY WITH ASTM D -2467 SOCKET TYPE. SOLVENT
CEMENT SHALL COMPLY WITH D -2564.
2. CONDENSATE DRAINS FROM AIR CONDITIONING UNITS: "PVC"
SCHEDULE 40 PIPE & FITTINGS.
SHEET LEAD FLASHING MOP. II\
WITH ROOFING MATERIAL.
3. DOMESTIC WATER ABOVE GROUND: TYPE L COPPER PIPE WITH WROUGHT
COPPER SOLDERED JOINT FITTINGS. TYPE K COPPER BELOW GROUND
PIPE ACCORDING TO ASTM B -42. TUBE ACCORDING TO ASTM B -88.
ALTERNATE FOR UNDERGROUND PIPE: CAST IRON WATER PIPE
ACCORDING TO ANSI A 21.6. STEEL PIPE (SCHEDULE 40,
GALVANIZED) ACCORDING TO ASTM A120 -68.
4. ALL CONTROL VALVES FOR DOMESTIC WATER SHALL BE CAST BRASS OR
B -88 BRONZE GATE VALVES.
5. PROVIDE DIELECTRIC FITTINGS FOR JOINING DISSIMILAR METALS.
HOT UJATER
SUPPLY
�-- 3/4" RELIEF LINE
OUTSIDE OF E3UILDING
SPILL 0I' AE30VE FINISHED
GROUND
a5ME PRESSURE 4 TEMPERATURE
RELIEF VALVE
ELIEF PIPE TO HAVE AN OPEI
�) DRAIN OUTSIDE OF BLDG. �
ELECT�RIC WATER HEATER [DETAL NTS.=
l
NOTE:
ANY VENT PIPE WITHIN 10' -0"
OF ANY DOOR, WINDOW,OR EXHAUST
OPENING SHALL EXTEND DOT LESS
THAN 3' -0" ABOVE SUCH.
TURN HEAD PIPE DOWN INTO STACK.
:ING.
CONSTRUCTION.
JLC C VG ROOF CONSTRUCTION
AS REQUIRED.
VENT THRU ROOF DETAIL
N.T.S.
Domestic Water Piping
1. PIPE HANGERS AND SUPPORTS: PROVIDE ADJUSTABLE HANGERS, INSERTS
BRACKETS, ROLLS, CLAMPS AND SUPPLEMENTARY STEEL AS REQUIRED FOR
PROPER SUPPORT OF PIPE LINES. HANGERS SHALL ALLOW FOR EXPANSION
AND CONTRACTION OF PIPE LINES AND COVERING TO RUN CONTINUOUSLY
THROUGH HANGERS.
2. SPACING AND SIZES
A. HORIZONTAL CARBON STEEL PIPE
PIPE SIZE ROD DIAMETER
UP TO 1-1/4" 3/8"
1 -1/2" & 2" 3/8"
B. HORIZONTAL COPPER PIPING
PIPE SIZE ROD DIAMETER
UP TO 1" 3/8"
1 -1/4" & 1 -1/2" 3/8"
2" 3/8"
NOTE:
ALL WASTE PIPING SLIP JOINTS SHALL
BE SOLDERED, OR SOLVENT CEMENTED
SO AS TO FORM A SOLID CONNECTION
PER FBC 405.8 CRITERIA, IF NO ACCESS
IS PROVIDED FOR SUCH PIPE CONNECTIONS.
MAXIMUM SPACING
8'
10'
MAXIMUM SPACING
6'
6'
8'
PLUMBING SYMBOLS
-*�
Hot + cold water
+
Cold water
+
Filtered cold water
SS
Steam supply
Q BLDG DEPT COMMENTS
Steam return
+
Gas
"
Waste / indirect waste
C°
Floor drain / funnel floor drain
WFloor
sink
(n General Notes & Details Plan
n.t.S.
ARCHITECTURE PLANNING INTERIORS
3Y`
::......
H E R S H
VITA L N
C ORAZZI NI
Luigi Vitalini
AR -13513
Pablo Corazzini
AR -91716
U
Florida
Project No.
I~
Distribution
Date
PERMIT SET
04 -17 -06
Q BLDG DEPT COMMENTS
06/08/06
cfl
co
C°
c�
O
.
s�
rl
CO
o
0
z
co
o
�
o
co
Sushi Maki
5812 S.W. 72nd St.
South Miami
Florida
Project No.
04033
Distribution
Date
PERMIT SET
04 -17 -06
Q BLDG DEPT COMMENTS
06/08/06
Sheet
ESI
ENERGY SCIENCES INC
CONSULTING ENGINEERS
ESBER ANDIROGLV, P.E.
MECH./ELEC. - 142454
2821 DOUGLAS ROAD
MIAMI. FL 33193
TEL 305- 448 -8828
FAX 305- 448 -7375
e -mail enerWObellsouth.net
P•204
H:�Proj a1 Drawicgs�D4033 Sushi h 00 x 24.00 inches)